Philippine venue
technical advance
Routing basis: Organizer’s live revision F CSV, checked 24 Nov 2026. It specifies 30 dated route stops at 28 distinct named venues: IC3 appears at stops 13 and 29; SMX Davao at stops 19 and 30. No alternate venues are named in the CSV. The CSV is the sole routing authority used here; the superseded PDF was not used. 1
Revision note, 24 November 2026: Routing Rev G is the current tour authority: 168,088 seats across 48 stops, of which the Philippine leg is unchanged at 113,000. The CSV supplied for this advance is the Rev F Philippine extract; its 30 stops, dates and 28 rooms are identical in Rev G, so every stop, date and room in this document stands. Rev G moved only the Vancouver room and the Canadian and US leg totals.
Read this as an advance, not an approval. Every listed capacity is the organizer’s planning figure, not a published venue capacity or technical, fire, occupancy or permit approval. Published comparative capacities are attributed separately and may refer to different rooms or layouts. The supplied timing assumption is a 22:00 show start plus 150 minutes, giving 00:30 on the next calendar day; this is not a confirmed permission. No venue, authority or supplier was contacted. Dates are show dates, not load-in authorizations. 1
Rigging safety: Both wall options below are assumed flown solely for evaluation. Actual wall weights, centers of gravity, hardware, support geometry, existing suspended loads, point reactions and complete load paths are unknown. Even a published venue rating is not an approval: each option needs an engineered, wall-specific load/rigging plot and written authorization from the venue and responsible structural engineer. “UNVERIFIED” is not a failure, a pass, or proof that an item does not exist.
Evidence method: This is an editorial synthesis of the supplied 28 venue-research records and their cited URLs, checked 24 Nov 2026, with no new research. An unresolved “not found” describes the material reviewed, not an exhaustive claim that a document or rating does not exist. Historical procurement, room or supplier claims are never treated as current venue certification. Public contacts are leads only; no production assignment is implied.
Common advance-critical checklist
Complete this checklist for every venue and, where repeated, for each date. Venue-specific priorities accompany each section: 1. Confirm the contracted building and room, exact loading address, event-date availability, operating status, authorized configuration, capacity and responsible venue/production contact. 2. Obtain current signed structural/fly drawings, floor-to-grid height, approved point count and coordinates, individual kg/point and total distributed kg, existing loads and signoff authority. Submit separate 9 × 4 m and 12 × 5 m designs with actual mass, center of gravity, hardware, load paths, point and cumulative loads and support geometry for engineered review and written approval. 3. Obtain the electrical single-line and venue electrician’s approval: service voltage, phases, available amperage per phase, tie-in, protection and stability, utility, generator requirement and permission, and any exclusive-provider terms. 4. Measure clear loading-door and lift dimensions, dock height, truck approach and turning, and internal freight path; secure day siting for a 53-ft trailer and tour bus, and any road-use, closure or parking permits. 5. Obtain stage and deck dimensions, height and certified kg/m² load rating, floor protection, proscenium/open configuration and risers; itemize house PA, lighting, video, backline, drapes, staffing, included and excluded equipment. 6. Obtain the current applicable ordinance and event-specific permits, sound limits, measurement points and exemptions, heritage/structural conditions, and a written hard event end allowing the proposed 00:30 finish. Confirm load-out or premises-vacate time separately; an imposed midnight load-out would be a separate scheduling conflict, not proof of a show-end curfew.
Venue advances
Stop group 01
Filoil EcoOil Centre
Route stop(s) and show date(s): 1 — 06 Feb 2027. Routed location: Pasig. Organizer planning capacity: 5,500. 1
Identity and routing: The routed Filoil EcoOil Centre is the arena at Col. Bonny Serrano Avenue / Santolan Road, Barangay Corazon de Jesus, San Juan City, Metro Manila; TicketMAX identifies Playtime FilOil Centre, FilOil Flying V Centre and The Arena in San Juan as names for that building 2. EcoOil also identifies the Filoil EcoOil Centre with San Juan 3. Routing says Pasig and gives 5,500 as a planning capacity 1; San Juan is a material city discrepancy, and 5,500 is not a verified show-specific occupancy. PhilSports Multi-Purpose Arena is a separate building in Pasig, not a substitute for this stop 4. Confirm the intended building and address before advancing.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from HOME venue management, for referral to its structural/facilities engineer; the specific engineering office is unverified 5. UNVERIFIED: roof/fly system and usable grid, point count and locations, maximum kg per point, total allowable distributed kg, supporting geometry, floor-to-grid height, rigging-plot approval requirements and approving engineer. No exact-venue point or total load rating was found publicly. 9 x 4 m flown LED wall: UNVERIFIED — cannot assess. 12 x 5 m flown LED wall: UNVERIFIED — cannot assess. For both, wall mass, center of gravity, individual and cumulative loads, approved point locations and supporting geometry are unknown; an engineered load plot and venue approval are required before either can be evaluated. The city reported that an organizer's lighting and audio trusses collapsed during ingress on 30 Oct 2026, with an investigation underway 5; this is not a finding about the permanent roof or its rating. Request current inspection and rigging restrictions from HOME's venue management/facilities engineering; the precise engineering office is UNVERIFIED.
-
Power: UNVERIFIED: building/show electrical service and voltage, phase count, available amperage per phase, tie-in location, distribution and protection, clean/stable power status, actual utility account or power provider, whether a generator is required or permitted, and any exclusive provider. Obtain the venue electrician's current single-line, tie-in and load capacity; the exact electrical office is UNVERIFIED.
-
Load-in: UNVERIFIED: loading-door width and height, dock height, truck entry and turning/access route, onsite siting for a 53-ft trailer for the day, onsite siting for a tour bus for the day, and any specific San Juan road-closure, truck or parking permit conditions. TicketMAX's parking FAQ says parking is very limited, while copied directions on the same page say it is ample 2; neither establishes large-vehicle access or availability. Request a measured route and parking/traffic plan from venue management and San Juan's Traffic and Parking Management Office 6.
-
Stage: UNVERIFIED: usable stage width/depth, deck height, stage-deck and arena-floor load ratings in kg/sqm, whether an event is presented with a proscenium or open configuration, and availability/specifications of house risers. Ask venue management for a current scaled plan, deck specifications, floor protection and approved configuration.
-
Curfews / restrictions: The planning curtain is 22:00 on 6 Feb 2027 and a 150-minute show would finish at 00:30 on 7 Feb 2027. Applicable hard event end: UNVERIFIED — conflict cannot be determined. Quantitative noise limit, measurement position and applicable conditions, event-specific barangay/city permit restrictions, heritage/structural restrictions, and any midnight load-out deadline: UNVERIFIED. A noise limit is not itself a hard event cutoff; a midnight load-out requirement, if imposed, would be a separate potential logistics conflict. The city index identifies a 2020 00:00–03:00 public curfew as applying during government-imposed community quarantine 7; its application to this 2027 event is not established. The published first page of San Juan Ordinance 78-2020 concerns amplified sound during quarantine and distance learning but omits the operative pages 8; do not treat its title as a current show cutoff or quantitative noise rule. 1
-
House equipment: UNVERIFIED: house PA, lighting, video/LED, backline, drapes, house risers, inventory condition, included staffing and specifically excluded items. A previous organizer's temporary lighting and audio trusses are reported by the city 5, but do not establish house inventory or availability for this event. Capacity figures do not imply any equipment is included.
-
Production contact: The City of San Juan directory lists Playtime Filoil Centre under ARENA with Bennett Palad and 0917-140-0484, but does not state a production/engineering title or arena email 6. The city identified HOME, Inc. as the independent venue manager/operator in its 30 Oct 2026 statement 5. Assigned tour production contact, venue technical email and precise facilities/engineering office: UNVERIFIED; request the responsible HOME venue management and engineering contacts. For permits and road access, the city directory lists Business Permit and License Office at bplo@sanjuancity.gov.ph, extensions 232–238, and Traffic and Parking Management Office at tpmo@sanjuancity.gov.ph, extensions 146–147 6.
Evidence limits: No public exact-venue technical rider, rated rigging or power schedule, loading specifications, date-specific event permit, or complete authoritative noise provisions were located. The city's available Ordinance 78-2020 PDF contained only its first page 8. An enforceable cutoff applying to this event is unverified; false for confirmed conflict means not established, not that the event is approved.
Advance-critical confirmations: - Reconcile San Juan against the routed Pasig label, establish the exact building and approved audience count, and request current post-incident inspection and restrictions 2 4 5. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 02
Batangas City Sports Coliseum
Route stop(s) and show date(s): 2 — 13 Feb 2027. Routed location: Batangas City. Organizer planning capacity: 5,000. 1
Identity and routing: The routed venue is the Batangas City Sports Coliseum on Delas Alas Drive, Batangas City, identified by the city’s facilities office 9 and TicketMAX 10. The city directory places Batangas City Sports Center (Coliseum) on Delas Alas Drive in Barangay 20 11; Apple Maps calls it Batangas City Sports Center – Coliseum but gives Santa Clara instead 12. Confirm the barangay and exact entrance. Do not substitute the separate Batangas Province Events Center in Barangay Bolbok 13. The 2024 city profile reports 4,500 seats 14, versus the organizer’s 5,000 planning figure 1; current event-specific permitted capacity is UNVERIFIED.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Coliseum Office / City General Services, for referral to the responsible structural engineer 11. UNVERIFIED: roof structure, fly system, approved point locations and count, maximum kg per point, total allowable distributed load in kg, rigging-plot approval process and floor-to-grid height. No venue/owner point or total load rating was found. The 9 × 4 m flown LED wall: UNVERIFIED, cannot be assessed. The 12 × 5 m flown LED wall: UNVERIFIED, cannot be assessed. For both, actual wall mass, center of gravity, point loads, approved attachment locations and supporting geometry are unknown; neither ratings alone nor wall size would establish safety without an engineered load/rigging plot and venue engineering approval. Request data from the Coliseum Office through City General Services and the responsible structural engineer; the specific venue engineering signatory is UNVERIFIED 11.
-
Power: UNVERIFIED: electrical service voltage, phases, amperage per phase, tie-in locations, cleanliness/stability, supplying utility, generator requirement, generator permission and exclusive production power provider. Request a panel schedule and tie-in details from the Coliseum Office and qualified facilities electrical personnel 9 11.
-
Load-in: UNVERIFIED: door clear widths and heights, loading dock height, truck approach and access, on-site 53-ft trailer siting for the day, tour bus siting for the day, and any event-specific city permit or road-closure conditions. The city charter lists parking among the facilities covered by its use service, but does not establish suitability or availability for these vehicles 11.
-
Stage: UNVERIFIED: stage width and depth, deck height, kg/sq m stage load rating, proscenium versus open configuration and house risers. Obtain an event-specific stage plan and engineering ratings from venue facilities management.
-
Curfews / restrictions: The 22:00 planning curtain and 150-minute show finish at 00:30 on 14 Feb 2027. Hard event end: UNVERIFIED — conflict cannot be determined. The city code §173(ss) describes a neighborhood-nuisance offense involving loud stereo or musical instruments, without a quantitative dB threshold or fixed cutoff in that clause; its present applicability and any amendments or event-specific conditions need confirmation 15. The code’s 21:00–04:00 movement curfew was expressly conditional on community quarantine, not evidence of an unconditional 2027 event cutoff 15. Quantitative noise limit, barangay/city permit conditions, and heritage or structural restrictions: UNVERIFIED. Midnight load-out condition: UNVERIFIED; if imposed, assess separately from show-end curfew. The city charter describes a request and endorsement process for facility use, not an approval for this event 11. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes and specifically excluded items. The separate provincial venue’s equipment must not be treated as equipment at this city coliseum 13. Request a current house inventory, exclusions and rental terms from the Coliseum Office 11.
-
Production contact: The city’s published process identifies the Office of the City General Services Officer, Administrative Division (Coliseum Office), for facility-use confirmation 11. General Services office: gsd@batangascity.gov.ph, +63 43 402 5223; City Engineer: engineering@batangascity.gov.ph, +63 43 723 6882 or +63 43 980 6615 11. Ask General Services to identify the responsible venue facilities/structural and electrical signatories; a named production contact and direct Coliseum Office email/phone are UNVERIFIED. The published city engineering office is a routing point, not a confirmed assigned venue engineer 11.
Evidence limits: No exact-venue primary technical specification, point or total rigging ratings, power capacity, date-specific hard event end, equipment inventory or identified venue engineering signatory was located. The city and Apple Maps disagree on the coliseum’s barangay; current event-specific capacity and permissions require confirmation.
Advance-critical confirmations: - Resolve the Barangay 20/Santa Clara discrepancy, distinguish the provincial venue, and reconcile the 4,500-seat city profile with the 5,000 planning figure 11 12 14 13. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 03
Dagupan City Astrodome
Route stop(s) and show date(s): 3 — 20 Feb 2027. Routed location: Dagupan. Organizer planning capacity: 4,000. 1
Identity and routing: The best match is Dagupan City People's Astrodome, an LGU-owned facility in Barangay Tapuac, Dagupan City, Pangasinan 16 17. A third-party listing places an immigration office at People's Astrodome, Tapuac Road, Tapuac District, Dagupan City 2400 18; an OpenStreetMap-derived map locates Dagupan Astrodome near 16.03593, 120.33247 19. Confirm the precise street and loading entrance with the venue. Do not substitute Tacloban City Astrodome, a different building in Tacloban City on Real Street 20. The Dagupan city council reported using its Astrodome as an evacuation center in 2025; event-date availability remains UNVERIFIED 21.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from City Engineer’s Office and the venue’s facilities management; the specific venue office is unverified 22. UNVERIFIED — roof structure and fly system, point count, approved locations, maximum kg per point, total allowable distributed load in kg, floor-to-grid height, and rigging-plot approval process. No exact-venue primary published point or cumulative ratings were found. 9 x 4 m flown LED wall: UNVERIFIED — cannot assess. 12 x 5 m flown LED wall: UNVERIFIED — cannot assess. For each wall, actual mass, center of gravity, point loads, approved locations, and support geometry are unknown; an engineered load/rigging plot and venue-authorized signoff are required before either wall can be assessed. Obtain engineering data from the City Engineer's Office and the responsible venue facilities management office; the precise facilities office is UNVERIFIED.
-
Power: UNVERIFIED — venue electrical service and voltage, phase count, amperage per phase, tie-in location, clean/stable status, whether a generator is required or permitted, and any exclusive production-power provider. The city posted a 2025 solicitation for Astrodome genset housing 23; this does not establish an installed or usable generator, its capacity, or permission for touring equipment. A 2010 energy regulator decision identifies Dagupan as part of DECORP's franchise area 24; the Astrodome's actual electrical supplier and event arrangements remain UNVERIFIED.
-
Load-in: UNVERIFIED — load-in door clear width and height, dock height, truck access route and turning clearance, onsite daytime 53-ft trailer siting, daytime tour-bus siting, and any specific city permits or road closures. Obtain an entrance plan, measured clearances, vehicle access hours and written parking/road-use conditions from the venue and responsible city offices.
-
Stage: UNVERIFIED — stage dimensions, deck height, deck load rating in kg/sqm, proscenium versus open configuration, and available house risers. A planning capacity is not evidence of a stage specification.
-
Curfews / restrictions: A planned 22:00 curtain and 150-minute show finish at 00:30 on 21 Feb 2027. Hard event end: UNVERIFIED — conflict cannot be determined. Applicable quantitative noise limits, jurisdiction and conditions: UNVERIFIED; a noise rule is not automatically a hard event cutoff. The city's permit page covers concerts and Astrodome rental 16; the 2022 city charter lists POSO and police endorsements for concerts 25. Current and event-specific permit, barangay, heritage and structural conditions are UNVERIFIED. Midnight load-out deadline: UNVERIFIED; if imposed, it would conflict separately with the planned finish, but is not by itself proof of a hard show-end curfew. 1
-
House equipment: UNVERIFIED — house PA, lighting, video, backline, drapes, risers and any specifically excluded items. Obtain an itemized inventory with specifications, condition, included/excluded scope, labor and rental terms.
-
Production contact: Venue facilities manager and assigned production contact: UNVERIFIED. For engineering, the City Engineer's Office is an appropriate public lead; the city directory lists Engr. Josephine M. Corpuz as City Engineer and (075) 522-1048 22. The 2022 city charter gives the office email engineersdagupan@gmail.com 25; neither source assigns her as the event's production contact. For the mayor's permit process, the city's One Stop Business Center is listed in the permit procedure 16, with directory numbers (075) 649-6951 and (075) 653-6897 22. Confirm the responsible venue operator and current contacts.
Evidence limits: Public sources did not provide venue-specific rigging or electrical capacities, loading/stage specifications, an equipment inventory, or an applicable hard show-end curfew. The city charter is a published 2022 source and current permit requirements need confirmation. The precise venue facilities manager and production contact remain unverified.
Advance-critical confirmations: - Confirm the Tapuac building and loading entrance, event-date availability and responsible facilities operator; distinguish the separate Tacloban Astrodome 17 20 21. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 04
Baguio Convention Center
Route stop(s) and show date(s): 4 — 06 Mar 2027. Routed location: Baguio. Organizer planning capacity: 3,000. 1
Identity and routing: The routed Baguio Convention Center is now called Baguio Convention and Cultural Center (BCCC), a city-owned facility under general supervision of the City Administrator’s Office 26. Its venue page lists Governor Pack Road, Baguio City 27; Apple Maps lists the Baguio Convention Center at UP Drive 28. Confirm the exact gate and which road address to use: the differing road descriptions alone do not establish two buildings. The separate Cordillera International Convention Hall is listed at Country Club Road and is not the routed venue 29. Routing plans for 3,000 1, while the city’s rental-manual announcement described the BCCC Full Hall maximum as 2,000 26; current approved capacity, seating configuration and the contracted room are UNVERIFIED. Do not add the basement or other rooms to reach the planning number.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from BCCC management through the City Administrator’s Office, for referral to the responsible structural engineer 26. UNVERIFIED: roof structure and fly system, point count and locations, maximum kg per point, total allowable distributed kg, floor-to-grid height and rigging-plot approval process. No exact-venue point or cumulative rating was found in a public primary source. The 9 × 4 m flown LED wall: UNVERIFIED, cannot assess. The 12 × 5 m flown LED wall: UNVERIFIED, cannot assess. Wall mass, center of gravity, individual point loads, approved hang locations and supporting geometry are unknown for both; even published venue ratings alone would not establish suitability without the actual engineered loads and plot and venue engineering approval. Ask BCCC management under the City Administrator’s Office to identify the responsible facilities/structural engineer 26; the specific engineering office and approver are UNVERIFIED.
-
Power: UNVERIFIED: site service voltage and phases, amperage available per phase, tie-in location, clean/stable supply, whether a generator is required or permitted, and any exclusive electrical or generator provider. Historical local reporting on late-2015 electricity bills named Benguet Electric Cooperative (BENECO) as the center’s distribution utility, but this does not verify the present provider or technical capacity 30. Request current site electrical documents and a show-specific power plan from venue management and its responsible electrical engineer; the exact engineering office is UNVERIFIED.
-
Load-in: UNVERIFIED: loading-door clear width and height, dock height, truck approach and access, turning and unloading route, and permission and space to site a 53-ft trailer and a tour bus onsite for the day. Specific city or barangay vehicle permits, road-closure conditions and any approved truck route are UNVERIFIED. Confirm the actual loading gate in light of Governor Pack Road versus UP Drive address listings 27 28.
-
Stage: UNVERIFIED: usable stage width and depth, deck height, load rating in kg/m², proscenium versus open configuration, and house risers. Obtain dimensioned stage drawings and a current rated deck specification from venue management’s responsible engineer; the precise engineering office is UNVERIFIED.
-
Curfews / restrictions: A 22:00 planning curtain plus 150 minutes ends at 00:30 on 7 March 2027, the following calendar day. Applicable hard event end: UNVERIFIED — conflict cannot be determined. Baguio police summarize City Ordinance 44-2018 as restricting excessive, unnecessary or unusually loud audio in residential areas, subdivisions and public streets from 22:00 to 05:00; the advisory also describes a prohibition on loud sounds within 200 m of schools, places of worship and hospitals, with specified exemptions 31. The city’s Environment Code advisory describes restrictions on unreasonable disturbing noise in residential areas from 21:00 to 06:00, including disturbance from equipment and loading/unloading, and refers to national noise standards 32. Whether these conditions apply to this indoor event, nearby receptors or its load-out is UNVERIFIED; a venue-specific dB limit is UNVERIFIED. These are noise restrictions, not a proven hard show-end time. Barangay/city event permit conditions, heritage or structural restrictions, and any midnight load-out deadline are UNVERIFIED; a midnight load-out deadline, if actually imposed, would separately conflict with the planned finish. Confirm all conditions and exemptions in writing. 1
-
House equipment: The city’s rental-manual announcement lists multimedia projectors and LED video walls as extra-charge add-ons 26; availability for this date, specifications and inclusion in this booking are UNVERIFIED. House PA, lighting, video inventory beyond that listing, backline, drapes, package inclusions and specifically excluded items are UNVERIFIED; do not assume equipment is absent or included from room capacity.
-
Production contact: BCCC’s public venue page lists telephone +63 74 446 2009 and email baguiocc2022@gmail.com 27. The City Tourism, Culture and Arts Office also publishes (074) 446-2009 as its support hotline 33. The City Administrator’s Office is identified by the city as the general supervising office 26. No named production contact or assigned technical engineer is verified. Ask venue management to identify its facilities/structural and electrical engineering contacts and the authorized rigging signatory; the exact office and individual are UNVERIFIED.
Evidence limits: No public exact-venue structural ratings, electrical service capacity or enforceable event-end deadline were verified. Police and city environmental-code advisories were read, but the full current operative ordinance text and its site-specific application were not independently verified. The venue social page intermittently presents a login wall; no login or contact was attempted.
Advance-critical confirmations: - Confirm the booked hall and entrance, reconcile the city’s 2,000 Full Hall maximum with the 3,000 plan, and obtain current site-specific noise interpretation 26 27 28. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 05
Angeles University Foundation Sports Arena
Route stop(s) and show date(s): 5 — 13 Mar 2027. Routed location: Angeles City. Organizer planning capacity: 3,500. 1
Identity and routing: Best match: AUF Sports and Cultural Center, on the AUF main campus in Angeles City, Pampanga 34 35 36. AUF calls it the Sports and Cultural Center 34; a basketball report calls the gym the Angeles University Foundation Sports Arena and Cultural Center 37. An independent map places the building on MacArthur Highway at approximately 15.14434, 120.59527 38; exact delivery entrance and barangay are UNVERIFIED. AUF lists a separate Santa Barbara campus 34; the Bren Z. Guiao Convention Center in San Fernando is a different venue and must not be substituted 39. A 2020 report identifies the main game court on the fourth floor and a practice court on the second floor 37; the exact hall contracted for this tour is UNVERIFIED. The routed 3,500 is an organizer planning figure, not a verified authorized event capacity 1.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from AUF Fitness, Sports and Recreation Center, for referral to facilities engineering 40. Roof structure, fly system, point count and locations, maximum kg per point, total allowable distributed kg, floor-to-grid height and rigging-plot approval process are UNVERIFIED; no venue-published ratings were located. For a flown 9 x 4 m LED wall: UNVERIFIED, no pass/fail assessment is possible. For a flown 12 x 5 m LED wall: UNVERIFIED, no pass/fail assessment is possible. For each, wall mass, center of gravity, individual point and cumulative loads, approved hang locations and supporting geometry are unknown; even published venue ratings alone would not establish suitability without the actual engineered wall loads and plot and the responsible operator's approval.
-
Power: Show service voltage, phase count, amperage per phase, tie-in location, clean/stable status, generator requirement, generator permission and exclusive production power provider are UNVERIFIED. Angeles Electric Corporation states that its distribution franchise area is Angeles City 41; the arena's actual supply account and any show-provider exclusivity are UNVERIFIED.
-
Load-in: Door width and height, loading dock height, truck approach and access, internal freight route and lifting equipment, day-long onsite siting for a 53-ft trailer and tour bus, and specific city permit or road-closure conditions are UNVERIFIED. A 2020 sports report placed the main game court on the fourth floor and a practice court on the second floor 37; neither a freight route nor the contracted event floor is established by that report.
-
Stage: Stage dimensions, deck height, kg/sqm deck load rating, proscenium versus open configuration, and availability of house risers are UNVERIFIED. AUF describes an events hall and a Robbins All-Star Maple basketball floor at the center 34; this is not a stage specification or floor loading certificate.
-
Curfews / restrictions: UNVERIFIED — conflict cannot be determined: hard event end, authoritative applicable quantitative sound restriction and measurement conditions, barangay/city permit conditions, and any heritage or structural restrictions are unverified. A 22:00 curtain plus 150 minutes yields a planned show finish of 00:30 on 14 Mar 2027, the following calendar day. A 2015 news report describes Angeles City Ordinance 366 concerning videoke and similar devices 42; the actual current ordinance text, its concert applicability, and any numerical limit or cutoff for this show are UNVERIFIED. A noise rule is not automatically a hard show-end curfew. A midnight load-out deadline is also UNVERIFIED; if imposed it would separately require a load-out schedule review and would not alone prove an event-curfew conflict. 1
-
House equipment: House PA, lighting, video, backline, drapes, house risers and specifically excluded items are UNVERIFIED. AUF describes basketball goals and a maple basketball floor 34, not a concert production inventory; the routed planning capacity does not establish equipment availability.
-
Production contact: AUF's Fitness, Sports and Recreation Center says it manages schedules and use of sports facilities and equipment 40; the precise facilities engineering office and the assigned production contact are UNVERIFIED. A visiting academic facility reported Jeffrey Jervoso as AUF Sports and Cultural Center athletic director and building manager on 29 Aug 2025 43; his current role and assignment to this tour are UNVERIFIED. AUF published 0917 303 6914 for Jervoso in a 2024 volleyball-tryout notice, not as a production line 44. AUF's general website footer lists +63 45 625 2888 ext. 1788 and admissions@auf.edu.ph; these are admissions contacts, not verified venue-production contacts 40. Request referral to the center's current building manager and responsible facilities/structural and electrical engineers.
Evidence limits: No publicly accessible exact-venue rigging ratings, show electrical capacity, concert technical rider, current official ordinance text, or show-specific permits were located. The contracted hall, current contact assignment, and applicability of any noise or event restrictions remain unverified.
Advance-critical confirmations: - Confirm the main-campus contracted hall and event floor, and establish a measured freight route and current school engineering contact 34 37. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 06
Imus Sports Complex
Route stop(s) and show date(s): 6 — 20 Mar 2027. Routed location: Cavite. Organizer planning capacity: 4,000. 1
Identity and routing: Best-supported match is City of Imus Sports Complex, General Castañeda Street, Imus, 4103 Cavite, beside Imus Cathedral 45. Imus is the city and Cavite the province, not an identification of Cavite City 45. The city's charter separately lists the Imus Fitness Center in Bucandala III and the City of Imus Grandstand and Track Oval in Malagasang I-G; neither should be substituted for the Sports Complex 46. A volleyball directory labels an 'Imus Sports Center' as Bacoor without a precise street address 47: whether this is a different building or an erroneous listing is UNVERIFIED. Confirm the booked venue and address with the organizer. Licensed event capacity for the intended configuration is UNVERIFIED.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from City of Imus Sports Development Unit and City Engineer; venue-specific signatory unverified 46 48. Roof/fly system, point count, per-point maximum kg, total allowable distributed load in kg, floor-to-grid height, approved hanging locations and rigging-plot approval process: UNVERIFIED. Public exact-venue point and cumulative ratings were not located. 9 × 4 m flown LED wall: UNVERIFIED — cannot assess. 12 × 5 m flown LED wall: UNVERIFIED — cannot assess. Both need actual wall mass, center of gravity, individual and cumulative point loads, approved points, supporting geometry, engineered plot and written venue/structural signoff; ratings alone would not establish either wall is safe. Request engineering information through the City of Imus Sports Development Unit and City Engineer; the precise venue engineering authority is UNVERIFIED 46 48.
-
Power: Service voltage/type, number of phases, amperage per phase, tie-in location, clean/stable status, whether a generator is required or permitted, and any exclusive electrical or production provider: UNVERIFIED. No exact-venue published electrical capacity was located; request a measured distribution plan and electrician's approval.
-
Load-in: Loading door clear widths/heights, dock height, truck access and turning, onsite daytime 53-ft trailer siting, daytime tour-bus siting, and applicable city permits or road-closure conditions: UNVERIFIED. Request a route plan and written parking and loading permission; do not assume street space is available.
-
Stage: Stage dimensions, deck height, floor/deck load rating in kg/sqm, proscenium versus open configuration, and house riser availability: UNVERIFIED. Request dimensioned plans and a current engineer-approved deck rating.
-
Curfews / restrictions: Planning curtain 22:00 on 20 Mar 2027 plus 150 minutes ends at 00:30 on 21 Mar. Applicable enforceable hard event end: UNVERIFIED — conflict cannot be determined. Cavite's information office identifies Provincial Ordinance 325-2021 as amending Ordinance 166, whose title addresses excessive noise in residential areas and along public streets/roadsides 49; the operative text, present status and applicability to this indoor show are UNVERIFIED, as is any quantitative dB restriction. Noise limits are not automatically a hard event cutoff. Barangay/city permit conditions, heritage or structural restrictions, and a midnight load-out deadline are UNVERIFIED; a midnight load-out deadline, if imposed, would create a separate potential load-out scheduling conflict. The city charter describes an application and permit process for the complex but does not establish this event's conditions 46. 1
-
House equipment: The city charter lists a Sports Complex rental option with lights and exhaust fan, and another with air-conditioning and VIP rooms 46; this is not a production-lighting specification or inventory. PA, show lighting, video, backline, drapes and specifically excluded items: UNVERIFIED. Request an itemized house inventory, operating condition, included package and exclusions.
-
Production contact: City of Imus Sports Development Unit handles the public-facility reservation process with the City Administrator's Office 46. The city identifies Mr. Jericho F. Reyes as Sports Development Unit OIC 50, not as this tour's assigned production contact. City directory lists Sports Development local 217, City Administrator local 601 and City Engineer local 403 51; the city publishes general landlines +63 46 888 9910 and +63 46 888 9912 52. Venue-specific production contact and email: UNVERIFIED. Request referral to the actual facilities-management and structural/electrical engineering authority; the precise responsible office is UNVERIFIED.
Evidence limits: No venue-specific certified rigging, stage, electrical or load-in specifications, current enforceable event cutoff, quantitative applicable noise limit, or assigned production contact were found. City booking address and Bacoor listing require reconciliation; provincial ordinance operative text, current status and applicability to this show remain unverified.
Advance-critical confirmations: - Confirm the General Castañeda Street booking against the Bacoor-labeled listing and secure the applicable actual ordinance and permit conditions 45 47 49. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 07
Quezon Convention Center
Route stop(s) and show date(s): 7 — 03 Apr 2027. Routed location: Lucena. Organizer planning capacity: 3,000. 1
Identity and routing: The routed venue is the Quezon Convention Center at Quezon Capitol Compound, Belen Drive, Barangay 10, Lucena City, Quezon 53 54. The provincial charter identifies it as a provincial facility managed by the Economic Enterprise Unit (EEU) 53. Do not confuse it with Northern Quezon Convention Center, Government Complex, Brgy. Comon, Infanta 55, or Southern Quezon Convention Center, Brgy. Tabing Dagat, Gumaca 56. The organizer's 3,000 planning capacity is not a verified occupancy limit 1; exact event space and approved show configuration remain UNVERIFIED.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Quezon Provincial Economic Enterprise Unit and Provincial Engineer 53 57. UNVERIFIED: roof and fly system, point count, maximum kg per point, total allowable distributed load in kg, floor-to-grid height, approved points, and rigging-plot approval requirements. No exact-venue point or cumulative rating was found in public primary material. The 9 × 4 m flown LED wall is UNVERIFIED and cannot be assessed; the 12 × 5 m flown LED wall is separately UNVERIFIED and cannot be assessed. Both require the actual wall mass, center of gravity, point loads, approved locations, supporting geometry, engineered plot and venue engineering approval; do not infer a pass from size or venue rating alone.
-
Power: UNVERIFIED: service voltage and capacity, number of phases, amperage per phase, tie-in location, clean/stable power, whether a generator is required or permitted, the specific utility supplying this venue, and any exclusive provider. The EEU's general electricity-billing procedure for provincial facilities references a Meralco billing statement, but does not identify this venue's supply or show service 53.
-
Load-in: UNVERIFIED: loading-door width and height, dock height, truck approach and access, onsite 53-ft trailer siting for the day, onsite tour-bus siting for the day, and any specific Lucena city permit or road-closure conditions.
-
Stage: The provincial charter describes a basketball court inside the Quezon Convention Center 53. Stage width and depth, deck height, load rating in kg/m², proscenium versus open configuration and house risers are UNVERIFIED; a court is not evidence of a particular show-stage configuration.
-
Curfews / restrictions: A 22:00 planning curtain on 3 Apr 2027 1 plus a 150-minute show ends at 00:30 on 4 Apr 2027. Hard event end, applicable quantitative noise limits and their jurisdiction and conditions, barangay/city permit conditions, and heritage or structural restrictions are UNVERIFIED. No applicable enforceable hard event end earlier than 00:30 was verified: UNVERIFIED — conflict cannot be determined. Noise limits would not by themselves establish a hard show cutoff. A possible midnight load-out requirement and any separate load-out conflict are also UNVERIFIED. 1
-
House equipment: House PA, lighting, video, backline, drapes, risers and specifically excluded or extra-charge items are UNVERIFIED. The organizer's capacity figure does not establish an equipment inventory.
-
Production contact: Provincial Economic Enterprise Unit: the charter lists it as the QCC facility-management office, with its office on the first floor of the center; (042) 785-8991, economicenterpriseunit@gmail.com, and 0933 812 6669 53 58. The charter names Melvin Viray for QCC and Alcala Sports Complex in the records/scheduling workflow, not as an assigned production contact 53. For engineering data, request referral to the Office of the Provincial Engineer; its directory lists Engr. Johnny A. Pasatiempo, (042) 788-7736, peo_quezonprovince@yahoo.com 57. The exact venue production engineer, structural signoff authority and assigned show contact are UNVERIFIED.
Evidence limits: No exact-venue public primary-source technical ratings, house inventory, applicable quantitative Lucena noise rule, or enforceable hard event cutoff were located. The responsible office for structural signoff and the actual show contact remain unverified; only public material was reviewed and no one was contacted.
Advance-critical confirmations: - Confirm the Lucena Capitol Compound room rather than either Infanta or Gumaca center, and obtain the correct provincial engineering signatory 53 55 56. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 08
Jesse M. Robredo Coliseum
Route stop(s) and show date(s): 8 — 17 Apr 2027. Routed location: Naga. Organizer planning capacity: 3,500. 1
Identity and routing: Jesse M. Robredo Coliseum is the former Naga City Coliseum, renamed by City Ordinance 2012-043 59. The city directory places it on Ninoy & Cory Avenue, Barangay Triangulo, Naga City 60, and the city event directory identifies Naga City, Camarines Sur 61. The city lists Naga City Gymnasium, Naga City Civic Center and the Jesse M. Robredo Museum auditorium separately; do not substitute them 62. The city describes 12,000 seats 63; this is not a current event-specific licensed capacity or validation of the organizer's 3,500 planning figure. The city said in October 2026 that the retrofit would be re-bid after a failed first bid; availability and work status on 17 Apr 2027 are UNVERIFIED 64.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from City Parks and Recreational Facilities Management Office and City Engineer 65 66. UNVERIFIED: roof/fly system, approved point count, maximum kg per point, total allowable distributed load in kg, floor-to-grid height, and venue rigging-plot approval process; no venue/owner/government point or cumulative ratings were found. The city reported retrofit rebidding after bidders raised concerns about the condition of the structure following inspection 64. For a flown 9 × 4 m LED wall: UNVERIFIED, cannot assess. For a flown 12 × 5 m LED wall: UNVERIFIED, cannot assess. Each requires the actual wall mass, center of gravity, point loads, approved locations, supporting geometry, engineered plot and responsible engineering/venue approval; no pass/fail is possible from wall dimensions or venue ratings alone.
-
Power: UNVERIFIED: service voltage and configuration, number of phases, available amperage per phase, tie-in location, power quality and stability, named supplying utility, whether a generator is required, whether a generator is permitted, and whether an exclusive provider applies. No primary-source venue power-capacity value was found.
-
Load-in: UNVERIFIED: load-in door width and height, dock height, truck approach and access, whether an onsite 53-ft trailer can be sited for the day, whether a tour bus can be sited for the day, and any applicable city permits, road-closure or access conditions. Do not infer vehicle suitability from a general parking listing.
-
Stage: UNVERIFIED: stage/deck dimensions, deck height, floor or deck load rating in kg/m², proscenium versus open configuration, and availability or specifications of house risers.
-
Curfews / restrictions: A 22:00 curtain with 150 minutes of performance ends at 00:30 on 18 Apr 2027. Hard event end: UNVERIFIED — conflict cannot be determined. Quantitative sound level limit applicable to this concert: UNVERIFIED. The text of Naga City Ordinance 36 of 1949 restricts noisy promotional use of specified sound devices within 50 m of government offices, school buildings, hospitals or maternity clinics at 08:00–12:00 and 17:00–24:00, where it causes unnecessary disturbance or nuisance, with a mayoral special-permit exception 67; its current validity and applicability to this site and event are UNVERIFIED, and it is not itself an established concert cutoff. The city facilities charter describes a mayoral permit request specifying the facility, date, time and purpose 62; current barangay/city event permit conditions, venue-specific heritage or structural restrictions, and any midnight load-out condition are UNVERIFIED. A midnight load-out condition, if imposed, would need separate assessment and is not by itself a hard event-end finding. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes and any specifically excluded items. The sound-system and lighting entries in the city charter are under Naga City Gymnasium, not the coliseum 62; they cannot be used as this venue's inventory.
-
Production contact: The city lists the City Parks & Recreational Facilities Management Office as responsible for functionality and maintenance including JMR Coliseum; its published office head is Engr. Francisco Paulo Pastor S. Lim, Engineer II / Office Head, email cprfmo@naga.gov.ph 65. The city directory lists office phones 8819007, 4950050 and 4731700 60. This is an office contact, not a named tour production representative. For engineering records, the City Engineer’s Office publishes ceo@naga.gov.ph and +63-54-871-2050 ext. 1060 / +63-54-205-2980 ext. 1060 66. The City Mayor’s Office is the office identified in the facilities-use charter 62; its published contact is cmo@naga.gov.ph, +63-54-871-2050 ext. 2010 or +63-54-205-2980 ext. 2010 68. The actual assigned event production contact and rigging signatory are UNVERIFIED.
Evidence limits: No public exact-venue rigging, power, stage or load-in specification or enforceable event-end cutoff was verified. Retrofit progress, 2027 availability, engineering approvals and event-specific permit/noise conditions remain unverified.
Advance-critical confirmations: - Confirm retrofit status, current structural certification and availability for the April date, and distinguish the coliseum from the city gym 62 64. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 09
Ilocos Norte Centennial Arena
Route stop(s) and show date(s): 9 — 24 Apr 2027. Routed location: Laoag. Organizer planning capacity: 3,000. 1
Identity and routing: The Palarong Pambansa venue page identifies Ilocos Norte Centennial Arena in Laoag City, Ilocos Norte, matching the routed city 69. The provincial charter locates the arena's South Wing at 47 Ablan Avenue, Barangay 3, Laoag City 70; a travel listing expands the street to Gov. Roque B. Ablan 71. The separate Ferdinand E. Marcos Stadium and Centennial Arena are components of the same sports complex 72. Laoag City Auditorium is separately listed from the arena 73. Neither is a substitute venue. Exact event entrance and on-site location remain UNVERIFIED.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Provincial Sports Office, for referral to the arena’s responsible engineer 70. UNVERIFIED: roof structure and fly/grid system, point count, maximum kg per point, total allowable distributed kg, approved positions and floor-to-grid height; no exact-venue owner or government point or total rating was found. For a 9 x 4 m flown LED wall: UNVERIFIED, cannot assess. For a 12 x 5 m flown LED wall: UNVERIFIED, cannot assess. For each, wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown; even published venue ratings alone would not establish suitability without the actual wall details, engineered loads and plot, and written venue/structural-engineer approval. Obtain the applicable engineering documents through the Provincial Sports Office and venue facilities/engineering; the specific approving technical office and assigned engineer are UNVERIFIED 70.
-
Power: UNVERIFIED: on-site electrical service and voltage, phase count, usable amperage per phase, tie-in location, clean/stable power, generator requirement or permission, and any exclusive provider. INEC lists Laoag coverage in its area offices, but this does not establish the arena's actual supply, show-power contractor or exclusivity 74. Obtain a show-specific electrical schedule and signoff from venue facilities/engineering via the Provincial Sports Office 70.
-
Load-in: UNVERIFIED: loading and door widths/heights, dock height, truck approach and access, on-site 53-ft trailer siting for the day, tour-bus siting for the day, and any Laoag city or barangay permit or road-closure conditions. Request surveyed route, turn and gate dimensions, ground/parking permissions and date-specific traffic conditions; the specific facilities office is UNVERIFIED.
-
Stage: UNVERIFIED: stage width and depth, deck height, deck/floor rating in kg/sqm, proscenium versus open configuration, and availability or dimensions of house risers. The provincial event page identifies a basketball court but does not publish a show-stage specification 69. Seek dimensioned plans and certified floor/deck data from venue facilities/engineering through the Provincial Sports Office 70.
-
Curfews / restrictions: Planning assumption: 22:00 curtain on 24 Apr 2027 plus 150 minutes ends at 00:30 on 25 Apr 2027. Hard event end: UNVERIFIED — conflict cannot be determined. Laoag police identify City Ordinance 13-2025-026 as regulating videoke, karaoke and other high/loud sound-producing devices 75, but the full ordinance and its applicability to this concert were not verified. Local reporting attributes to a city councillor a Friday/Saturday 08:30–23:00 loud-sound window and describes exemptions including government-sanctioned activities; this is attributed reporting, not a confirmed show-specific enforceable cutoff 76. Applicable quantitative sound limit, event exemption, barangay/city permit terms, heritage or structural restrictions, and load-out deadline are UNVERIFIED. A midnight load-out deadline, if imposed, could separately conflict with this planned 00:30 finish; none has been verified. 1
-
House equipment: House PA, lighting, video, backline, drapes and specifically excluded items: UNVERIFIED. An OWWA 2025 request for quotation specified rental of LED, lights and sound for an event at the exact arena 77; it is an event procurement request, not evidence that these items are house inventory, available for this show, or absent. Request a current itemized included/excluded inventory and condition report.
-
Production contact: The provincial charter identifies the Provincial Sports Office as the office for use of provincial facilities and equipment, names Helen Rose M. Domingo in its office list, and lists its address as 2/F North Wing, Centennial Arena, Ablan Avenue, Laoag City, phone (077) 784-3840 70. The province's separate directory lists Helen Rose Molina-Domingo at Ferdinand E. Marcos Stadium and gives ilocosnortesportsdevelopment@yahoo.com and insports@ilocosnorte.gov.ph 78; confirm which office location and contact are current. She is not verified as this show's assigned production contact. The precise arena facilities/engineering or rigging-signoff office, named production representative, and direct production phone/email are UNVERIFIED; request referral from the Provincial Sports Office 70.
Evidence limits: No exact-arena official rigging, electrical, stage, loading or house-equipment specifications were found; the complete Laoag loud-sound ordinance and any event-specific permit or hard finish/load-out condition could not be verified. The province's official sources differ on the sports office's location.
Advance-critical confirmations: - Confirm the arena entrance and current Provincial Sports Office location, and obtain the authoritative current loud-sound ordinance and event-specific exemptions 70 75 78. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 10
Iloilo Convention Center
Route stop(s) and show date(s): 10 — 01 May 2027. Routed location: Iloilo City. Organizer planning capacity: 4,000. 1
Identity and routing: Iloilo Convention Center, also called ICC or ICON, is on Megaworld Boulevard, Iloilo Business Park, Mandurriao, Iloilo City 5000; the routed city matches 79 80 81. TIEZA places it between the hotels it calls Richmond and Marriott 79. It is not Courtyard by Marriott Iloilo’s separate nearby meeting venue 82. The specific hall allocation for this show is UNVERIFIED. Capacity requires reconciliation: TIEZA describes four first-floor halls together, 2,900 sq m, accommodating up to 2,400 persons without specifying a configuration 79; TPB’s 2026 directory lists the venue at 4,000 theater and 1,600 banquet 83, while an older TPB brochure lists 3,000 theater and 1,700 banquet 84. The routed 4,000 is a planning figure, not a verified show-specific occupancy or safety approval.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from ICC operations/facilities engineering via the convention-center contact 80. UNVERIFIED: roof and fly system, point count, maximum kg per point, total allowable distributed kg, approved point locations and supporting geometry, floor-to-grid height, and who approves a rigging plot. No exact-venue point or cumulative roof rating was located in the primary documents reviewed. 9 x 4 m flown LED wall: UNVERIFIED, cannot assess. 12 x 5 m flown LED wall: UNVERIFIED, cannot assess. For both, wall mass, center of gravity, point loads and geometry are unknown; no pass/fail is possible without the actual wall specification, engineered load calculations and plot, and venue/structural signoff. Seek ICC facilities management/engineering; the precise local office or assigned engineer is not publicly verified.
-
Power: MORE Power identifies itself as Iloilo City’s sole electric distribution utility 85; the convention center’s individual connection and supply arrangement are UNVERIFIED. Service voltage, phases, available amperage per phase, tie-in location, clean/stable power, whether a generator is required, whether a generator is permitted, and any exclusive event power provider are all UNVERIFIED. Citywide utility status is not a venue electrical capacity or exclusive production-vendor statement.
-
Load-in: Door dimensions, dock height, truck access/turning and entrance, onsite 53-ft trailer siting for the day, tour-bus siting for the day, and city permits/road-closure conditions are UNVERIFIED. A DOST procurement for an earlier ICC event proposed that DOST and/or the convention center arrange available temporary truck storage, but does not establish current parking or trailer accommodation 86. Iloilo City lists a Traffic and Transportation Management Office and Business Permits & Licensing Office as relevant confirmation leads 87.
-
Stage: Current show stage dimensions, deck height, deck live-load rating in kg/sq m, proscenium versus open configuration, and house risers are UNVERIFIED. A 2023 DOST event request specified a rented 5 m x 10 m x 1 m main stage and noted the stage platform was c/o Iloilo Convention Center 86. This is a historical event request, not a current permanent stage specification, certified load rating, or guarantee of availability.
-
Curfews / restrictions: A 22:00 curtain on 01 May 2027 plus 150 minutes ends at 00:30 on 02 May 2027. Hard event end: UNVERIFIED — conflict cannot be determined. Iloilo City’s 2020 public statement says City Regulation Ordinance 2015-162 adopted Ambient Noise Quality Standards 88, but the authoritative current text, applicable zone, measurement conditions, quantitative dB limit, amendments and application to this event are UNVERIFIED; a noise limit is not itself a hard show cutoff. Barangay/city event-permit conditions, heritage and structural restrictions are UNVERIFIED. A previous DOST event’s procurement specified dismantling by midnight 86; this was event-specific, not a standing 2027 rule. A midnight load-out condition, if imposed here, would separately require review because the planned show ends after midnight; its existence is UNVERIFIED. 1
-
House equipment: House PA, lighting, video, backline, drapes and specifically excluded items are UNVERIFIED. An earlier event procurement noted a stage platform c/o the convention center 86, but does not establish its present availability or a house inventory. Published room capacities do not establish equipment availability.
-
Production contact: The convention center’s public contact page lists Megaworld Boulevard, mobile +63 968 895 3295 and iloiloconventioncenter@gmail.com 80. Specific production contact, assigned officer and local engineering-office title are UNVERIFIED. TIEZA’s central directory lists Engr. Gregory A. Oller as Assistant Chief Operating Officer for Architectural and Engineering Services, with central direct line +63 2 8249 5983 and trunk +63 2 8249 5900 extensions 731–732 89; this is an agency engineering escalation, not evidence he is the assigned venue production contact. The 2026 TPB directory lists +63 45 599 8000 alongside ICC 83, but the older TPB brochure also lists 045 599 8000 for Quest Hotel and Conference Center Clark 84, so the directory number should not be relied on as an ICC line without confirmation.
Evidence limits: No venue-specific public engineering ratings, electrical capacity, current loading/parking specifications, event-specific hard end or applicable numerical noise conditions were verified. TIEZA’s venue page and government tourism directories disagree on capacities; current configured occupancy requires confirmation. No one was contacted.
Advance-critical confirmations: - Confirm the hall combination and licensed show layout; reconcile TIEZA and tourism-directory capacities and confirm the disputed phone number 79 83 84. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 11
University of St. La Salle Coliseum
Route stop(s) and show date(s): 11 — 08 May 2027. Routed location: Bacolod. Organizer planning capacity: 4,000. 1
Identity and routing: The routed room is the university's La Salle Coliseum, also called USLS Coliseum or St. La Salle Coliseum, inside the University of St. La Salle campus, La Salle Avenue, Bacolod City 6100, Negros Occidental 90 91. The separate Bacolod City coliseum is between Barangays Alijis and Tangub and is not the routed building 92. The organizer's 4,000 is a planning figure, not verified event capacity. The university's 2025–26 student handbook states 6,500 for a concert configuration, comprising 1,800 loge and 4,700 bleacher seats 93; its 2024–25 graduate handbook instead lists 8,000, including 1,200 floor, 800 loge and 6,000 bleacher seats 94. These different published figures/configurations require reconciliation and event-specific approval.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from USLS Coliseum office and Ancillary/Facilities Management Services 95 96. UNVERIFIED: roof/fly system, available point count and locations, maximum kg per point, total allowable distributed kg, floor-to-grid height, rigging-plot submission and approval procedure. No venue/owner/government point or total load ratings were found publicly. 9 x 4 m flown LED wall: UNVERIFIED—cannot assess. 12 x 5 m flown LED wall: UNVERIFIED—cannot assess. For each, wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown. An engineered wall-specific load/rigging plot and venue/structural signoff are required before any assessment; published venue ratings alone would not establish a pass. Request drawings and engineering limits through the university's Ancillary / Facilities Management Services and Coliseum office 95 96.
-
Power: UNVERIFIED: electrical service and voltage, phase count, amperage available per phase, tie-in location, supply quality/clean-stable status, actual utility provider, whether a generator is required or permitted, and whether an exclusive power provider is mandated. Request a current single-line diagram and technical confirmation from university facilities management and Electrical & Technical Works 95 96.
-
Load-in: UNVERIFIED: load-in door clear width/height, dock height, truck route/gate access, onsite daytime 53-ft trailer siting, onsite daytime tour-bus siting, and applicable city permits or road-closure conditions. The 2024–25 university handbook describes limited parking behind the Coliseum and restricts student/alumni parking there; this is not a tour-vehicle permission 94. The 2025–26 house rules require exits to remain clear and say wheeled props must not be dragged and must have thick rubber or carpet matting 93. Seek the approved vehicle plan and current access rules from the Coliseum office.
-
Stage: The university's 2025–26 student handbook describes a theater-style stage and says the space can switch between sports, seminar and concert setups 93. Exact stage dimensions, deck height, rated load in kg/sqm, actual proscenium versus open configuration, and house risers are UNVERIFIED. The handbook prohibits nailing/construction inside, prohibits painting and carpentry inside, requires prop clearance and directs users to staff about adhesives 93; event-specific application must be confirmed.
-
Curfews / restrictions: A 22:00 curtain on 08 May 2027 plus 150 minutes ends at 00:30 on 09 May 2027. Hard event end: UNVERIFIED — conflict cannot be determined. Bacolod City Ordinance 356 (2004), Arts. 2–3, gives A-weighted ambient-noise standards: its nighttime table lists Class AA 40, A 45, B 55, C 60 and D 65 dB, with the arithmetic median of at least seven readings at the point of maximum noise; the night period begins at 22:00 97. The scan prints the night endpoint as '5:00 P.M.'; obtain the authoritative current text/interpretation rather than silently correcting it. Class AA includes quiet areas such as those within 100 m of schools, but the applicable classification, measurement location, exceptions and event conditions are UNVERIFIED 97. A noise limit is not itself a hard show-end cutoff. Ordinance 326 has conditional noise/disturbance-related operating restrictions for covered amusement places near sensitive uses; applicability to this venue and event is UNVERIFIED 98. Barangay/city event permit terms, heritage restrictions, structural restrictions and any midnight load-out deadline are UNVERIFIED; a midnight load-out condition would need separate analysis and is not automatically an event curfew. 1
-
House equipment: The university's 2025–26 handbook describes a digital sound and lighting system and theater-style stage 93; models, inventory, working condition, operator, hire inclusion and suitability for this production are UNVERIFIED. PA components, detailed lighting, video, backline, drapes and specifically excluded rental equipment are UNVERIFIED. Separate house-use restrictions in that handbook prohibit candles, fireworks and other incendiary devices, laser pens, Styrofoam props/costumes/design, balloons, confetti and party poppers 93. Confirm current rules and any event-specific exceptions directly with the Coliseum office.
-
Production contact: University Coliseum office, located on the Coliseum's mezzanine according to the 2025–26 handbook 93. University's directory lists Coliseum local 153 and 435-0053, and Ancillary / Facilities Management Services Director local 221 and 435-2767; university trunkline +63 34 434 6100 95. The institutional officer page lists Revie M. Salvio under Ancillary Services/Facilities Management Services and associates bookstore@usls.edu.ph with that officer card 96; a 2025 university report identifies Salvio as director 99. The email is bookstore-branded, and a Coliseum-specific production email, show-assigned contact and current authority to sign off engineering are UNVERIFIED. Facilities management and Electrical & Technical Works are the best published university functions to request engineering data from 96.
Evidence limits: No current public roof/rigging load ratings, electrical capacity, load-in dimensions, event-specific permissions or enforceable hard event end found. The older and newer university handbooks differ on capacity; the city ordinance scan prints an apparently inconsistent nighttime end and the specific receiving-area class remains unverified. Confirm current handbook rules, classification and all event-specific engineering and permit conditions with the responsible offices.
Advance-critical confirmations: - Reconcile the university handbook capacities and resolve the applicable noise class and inconsistent scanned night-period endpoint; obtain current house and prop rules 93 94 97. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 12
Capiz Provincial Gymnasium
Route stop(s) and show date(s): 12 — 15 May 2027. Routed location: Roxas City. Organizer planning capacity: 2,500. 1
Identity and routing: Likely match: Capiz Gymnasium at Villareal Stadium, Barangay Tiza, Roxas City, Capiz; local reporting identifies the gym in the stadium and attributes the property to the provincial government 100. Mapcarta places Capiz Gymnasium at approximately 11.57425, 122.75878 101. The routed word 'Provincial' has not been independently verified as the building's formal name: confirm the booking and exact entrance/street address. It is not the Provincial Cultural and Sports Center across from the gym 102, nor the Dinggoy Roxas Civic Center at Barangay IV, Legaspi Street 103. PIA reports a 6,000-capacity gym, not an approved concert capacity 102.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Capiz Provincial General Services and Provincial Engineer; the gym’s signatory is unverified 104. UNVERIFIED: roof structure and fly system; approved rigging points and point count; maximum kg per point; total allowable distributed kg; floor-to-grid height; and plot review/signoff process. No exact-venue point or total-load ratings were found publicly. 9 × 4 m flown LED wall: UNVERIFIED; cannot assess. 12 × 5 m flown LED wall: UNVERIFIED; cannot assess. Wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown; neither wall can be assessed even from venue ratings alone without its actual engineered loads and plot and venue approval. Obtain the responsible venue facilities/engineering office and signed structural documentation.
-
Power: UNVERIFIED: service voltage, number of phases, amperage per phase, tie-in location, clean/stable supply, whether a generator is required or permitted, the actual utility supplying this building, and any exclusive event power provider. Request a current panel schedule and electrician-approved connection details.
-
Load-in: UNVERIFIED: loading door dimensions, dock height, truck route and access, onsite 53-ft trailer day siting, onsite tour-bus day siting, and specific Roxas City/barangay permits or road-closure conditions. Obtain a site plan and written vehicle and street-use approvals; do not assume space or permission.
-
Stage: UNVERIFIED: stage width/depth, deck height, deck or floor load rating in kg/m², proscenium versus open configuration, and availability of house risers. Obtain venue-specific plans and certified floor/deck ratings.
-
Curfews / restrictions: A 22:00 planned curtain plus 150 minutes ends at 00:30 on 16 May 2027, the following calendar day. Hard event end: UNVERIFIED — conflict cannot be determined. Roxas City police summarize Ordinance 043-2020 as restricting videoke and sound systems in residential areas from 22:00 to 05:00 unless properly soundproofed, with permits and limited extended hours for special/personal events 105. The full ordinance, amendments, applicable zoning, event-specific conditions and whether this show qualifies were not verified; this conditional noise summary is not proof of a hard event cutoff. An applicable quantitative decibel limit is UNVERIFIED. Barangay/city permit conditions, heritage/structural restrictions, and midnight load-out deadline are UNVERIFIED; a midnight load-out deadline, if imposed, would need separate assessment from the show-end curfew. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes and specifically excluded items. A reported general gym capacity is not an equipment inventory 102.
-
Production contact: Specific venue operator, facilities manager and assigned production contact: UNVERIFIED. The Capiz provincial directory lists the Provincial Engineer's Office, Engr. Edwin D. Villasis as Acting Provincial Engineer, (036) 620-0261 and capizpeo.cmgp@gmail.com; it also lists the Provincial General Services Office, (036) 620-1038 and pgsocapiz@gmail.com 104. These are public provincial office contacts, not verified venue production assignments. Ask the provincial government to identify the responsible facility operator and engineering signoff authority.
Evidence limits: The routed formal name and precise entrance remain unconfirmed; public research did not locate an exact-venue technical rider or engineered ratings, verified power capacity, full applicable ordinance text, event permit, or an assigned venue production contact. Police noise guidance is conditional and cannot establish a hard 00:30 show-end conflict.
Advance-critical confirmations: - Confirm the formal routed name, booked gym and exact entrance within Villareal Stadium, not the separate provincial center or civic center 100 102 103. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 13
IC3 Convention Center
Route stop(s) and show date(s): 13 — 05 Jun 2027; 29 — 20 Nov 2027. Routed location: Cebu City. Organizer planning capacity: 3,500. 1
Identity and routing: The routed IC3 is IEC Convention Center Cebu, 23 Minore Park, Pope John Paul II Avenue corner Cardinal Rosales Avenue, Cebu City 106; a venue directory places it in Barangay Luz 107. It was formerly the International Eucharistic Congress Pavilion 108. This is not the separately named Cebu International Convention Center (CICC) in Mandaue 109. No hall is specified in the routing. The organizer's 3,500 planning figure is not an approved show capacity; a 2016 report described proposed halls for 1,000–3,500 each, not the capacity of the unspecified booked configuration 108.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from IC3 administration for referral to facilities engineering; the current operator and signatory are unverified 107 110. UNVERIFIED: roof/fly system, point count, maximum kg per point, total allowable distributed load in kg, approved point locations, floor-to-grid height, and rigging-plot approval process. No venue/owner/government point or total load rating was found publicly. For the 9 x 4 m flown LED wall: UNVERIFIED — cannot assess. For the 12 x 5 m flown LED wall: UNVERIFIED — cannot assess. For both, actual wall mass, center of gravity, individual point loads, approved locations and supporting geometry are unknown; an engineered load/rigging plot and venue engineering approval are needed. Venue ratings alone, if later obtained, would not establish that either wall is safe. Request data from the responsible venue facilities management/engineering team; its precise office name is UNVERIFIED.
-
Power: UNVERIFIED: electrical service and voltage, phases, available amperage per phase, tie-in location, clean/stable status, whether a generator is required, whether one is permitted, electrical utility provider, and whether any power or generator provider is exclusive. Request the venue engineering team's current electrical schedule and tie-in requirements.
-
Load-in: A venue-directory listing describes a delivery ramp from the basement 111, but this is not a surveyed or certified loading specification. UNVERIFIED: load-in door clear sizes, dock height, truck access and turning route, suitability of the ramp, onsite 53-ft trailer siting for the day, onsite tour-bus siting for the day, and Cebu City permit or road-closure conditions for this event.
-
Stage: A venue-directory listing describes movable partitions in a ground-floor plenary 111; this does not establish the production-stage configuration. UNVERIFIED: stage width and depth, deck height, stage load rating in kg/sqm, proscenium versus open configuration, and house risers. The routed hall and the exact proposed stage must be confirmed.
-
Curfews / restrictions: The planned 22:00 curtain plus 150 minutes ends at 00:30 the following day: 06 Jun and 21 Nov 2027 respectively. Hard event end: UNVERIFIED — conflict cannot be determined. A copy of Cebu City Ordinance 2606 adds a conditional prohibition on unreasonably disturbing amplified noise near residential areas during specified public-health emergency or quarantine periods; it specifies Sunday use from 08:00 to 18:00 112. Applicability at this venue and on these dates is UNVERIFIED; this conditional noise provision is not proof of an ordinary hard event cutoff. The applicable quantitative dB restriction, measurement conditions, barangay/city permit terms, heritage and structural restrictions are UNVERIFIED. A November 2026 report describes a new comprehensive noise ordinance as proposed, not enacted; its final status is UNVERIFIED 113. Any separate midnight load-out deadline and its potential conflict with a 00:30 finish are also UNVERIFIED. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes and any specifically excluded items. Capacity or hall descriptions do not establish that production equipment is supplied; request the current inventory and exclusions from the venue.
-
Production contact: No assigned production contact, named technical officer, or precise public title for the facilities/engineering office was verified. A venue-trade listing gives IC3's general phone as +63 32 345 0546 and email as info@ic3.events 107; another directory gives an administration phone of +63 32 346 6969 and the same email 110. The conflicting numbers and their current validity are UNVERIFIED. The trade listing identifies Regent Property International as manager 107, while 2016 reporting identified Duros Land as operator and the Archdiocese of Cebu as owner 108; the current responsible operator is UNVERIFIED. Ask venue administration to route the advance to its facilities management/engineering team.
Evidence limits: No primary venue/owner engineering specification, show-specific permit, current authoritative site-applicable dB threshold or assigned production officer was verified; the venue social page required sign-in and the two public directory phone numbers differ. The current operator, hall allocation, venue technical ratings, and both 2027 permit and curfew conditions remain unverified.
Advance-critical confirmations: - For each date, confirm the IC3 hall and current operator, verify the conflicting directory phone numbers, and obtain separate overnight permits 107 110. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 14
Ormoc City Superdome
Route stop(s) and show date(s): 14 — 19 Jun 2027. Routed location: Ormoc. Organizer planning capacity: 3,000. 1
Identity and routing: The Department of Tourism identifies Ormoc City Superdome as a multipurpose indoor stadium in Ormoc, Leyte 114. The city’s 2025 charter places its Superdome office on Larrazabal St., Barangay South, Ormoc City 115. Trip.com gives Larrazabal Boulevard / San Pedro Street 116, whereas Taga Ormoc Daily describes Imelda Boulevard at Ormoc City Plaza 117; confirm the exact loading entrance and street naming. A commercial directory labels a GSIS address ‘Ormoc Astrodome, Magsaysay Boulevard’ 118; whether that entry refers to this building is UNVERIFIED. The Tacloban City Convention Center is a separate facility popularly called the Astrodome in Tacloban 119; do not substitute it or Ormoc’s separately listed sports complex or Juaton sports village 120. The routing’s 3,000 is an organizer planning figure, not a verified occupancy certification 1.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Ormoc City Superdome Office, for referral to the responsible structural engineer 115. UNVERIFIED: roof or fly system, approved suspension-point count and locations, maximum kg per point, total allowable distributed load in kg, floor-to-grid height, required rigging-plot approval and who signs it. Venue point and cumulative load ratings were not found in public primary specifications. The 9 × 4 m flown LED wall: UNVERIFIED; cannot be assessed without actual wall mass and center of gravity, engineered individual point and cumulative loads, approved locations and supporting geometry, and venue/engineer plot approval. The 12 × 5 m flown LED wall: UNVERIFIED on the same basis; no pass/fail or safety conclusion is possible. Request the Ormoc City Superdome Office to coordinate with the responsible structural engineer 115.
-
Power: UNVERIFIED: venue service voltage and configuration, number of phases, amperage per phase, show tie-in location, clean/stable status, whether a generator is required or permitted, and any exclusive power provider. LEYECO V says its distribution area includes Ormoc City 121; the Superdome’s actual meter, supply arrangement and show power capacity are not verified by that area-level statement. No venue capacity rating was found in public primary sources.
-
Load-in: UNVERIFIED: load-in door width and height, dock height, truck approach and access, on-site siting of a 53-ft trailer for the day, on-site tour-bus siting for the day, and any specific traffic, road-closure or city permit conditions. Confirm street and truck entrance against the differing public address descriptions 115 116 117.
-
Stage: UNVERIFIED: stage dimensions, deck height, deck load rating in kg/sqm, proscenium versus open configuration, and house risers. The city’s charter refers to hire of the Superdome court and facilities, not a certified stage specification 115.
-
Curfews / restrictions: A 22:00 curtain on 19 June 2027 plus 150 minutes ends at 00:30 on 20 June. Hard event end: UNVERIFIED — conflict cannot be determined. A local news outlet reports that Ormoc’s council approved Draft Ordinance No. 48, Series of 2026, describing a 22:00–06:00 amplified-sound restriction with exceptions including a possible mayoral permit to 02:00 122. The actual enacted text, effectivity, quantitative dB limit, exemptions and application to this event remain UNVERIFIED; this report is not proof of a hard event-end curfew. The city charter describes a clearance/permit from BPLO if necessary, a signed use contract and City Administrator approval 115; actual city and barangay conditions for this date are UNVERIFIED. Heritage and structural restrictions are UNVERIFIED. Midnight load-out deadline: UNVERIFIED; if imposed it would be a separate potential conflict with the 00:30 show finish, not proof of a show-end curfew. 1
-
House equipment: The city’s 2025 charter lists court-use rental packages including a sound system and differing levels of lights, with or without air conditioning 115. Their current availability and suitability are UNVERIFIED: concert PA inventory and coverage, show lighting fixtures/control, video, backline, drapes, any included or specifically excluded items, and staffing. The charter’s generic sound and lights wording is not a concert technical rider.
-
Production contact: Ormoc City Superdome Office: the 2025 city charter lists Virgie Ann O. Arreza as officer-in-charge and publishes office mobile 0936-911-2810, local 1045, and ormocsuperdome@gmail.com 115. An October 2026 city government announcement also identifies Virgie Ann Arreza as OIC-Superdome 123. These are office details, not a personal production assignment. Ask this office to identify the responsible facilities/structural and electrical engineering signatories; the assigned production engineer and direct technical contact are UNVERIFIED.
Evidence limits: No primary public structural or show-power ratings, actual noise ordinance text or event-specific permit conditions were located. A reported noise measure is not verified as applicable law for this event; resolve with the Superdome Office and responsible city authorities.
Advance-critical confirmations: - Confirm the Superdome loading address and current operator; obtain the authoritative enacted noise text and any event exemption 115 116 117 122. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 15
Lamberto Macias Sports Complex
Route stop(s) and show date(s): 15 — 26 Jun 2027. Routed location: Dumaguete. Organizer planning capacity: 3,000. 1
Identity and routing: The routed venue is the Lamberto L. Macias Sports & Cultural Complex, also styled Sports and Cultural Center, in Dumaguete, Negros Oriental; the provincial government uses both Center and Complex in one advisory 124. Mapcarta identifies the building at approximately 9.31191° N, 123.30066° E, plus code 8862+Q7, and lists the provincial government as operator 125. An exact street address is UNVERIFIED. The city lists Macias Sports Complex, Perdices Coliseum and Negros Oriental Convention Center as separate venues; do not substitute either neighboring venue 126. No city mismatch was found, but confirm the mapped building and booked room with the responsible operator. A provincial announcement closed the complex for maintenance on 3–25 July 2025, not the 2027 date; present condition and availability remain UNVERIFIED 127.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Negros Oriental Provincial Engineering and General Services; exact venue authority unverified 128. UNVERIFIED: roof structure/fly system, point count, maximum kg per point, total allowable distributed kg, floor-to-grid height, approved locations and rigging-plot/signoff procedure. No official exact-venue ratings were located. For a 9 × 4 m flown LED wall: UNVERIFIED — cannot assess. For a 12 × 5 m flown LED wall: UNVERIFIED — cannot assess. For both, wall mass, center of gravity, point loads, approved positions and supporting geometry are unknown; even published venue ratings alone would not establish suitability without the actual engineered wall loads and plot and approval. Seek the venue's responsible facilities management and provincial engineering office; the precise venue rigging authority is UNVERIFIED.
-
Power: NORECO II listed the complex in a scheduled feeder interruption on 16 May 2026; this is historical service evidence, not a guarantee of current supply or show reliability 129. UNVERIFIED: venue service voltage and phase configuration, available amperage per phase, tie-in location, clean/stable power, present utility provider, whether a generator is required or permitted, and exclusive production power provider. Dumaguete City Engineer's Office publishes a general temporary electrical service connection process; whether it or generator permits apply to this production is UNVERIFIED 130.
-
Load-in: UNVERIFIED: load-in door widths/heights, dock height, truck access/turning route, on-site 53-ft trailer day siting, tour-bus day siting, and city/barangay permit or road-closure conditions for this event. For a different event on 8–9 October 2026 the province specified a daytime one-way route via San Jose Extension and Perdices Coliseum to Macias, and parking in front of the complex and provincial engineering office 124; that historical arrangement does not authorize trailer, bus, road use or parking for 2027.
-
Stage: UNVERIFIED: stage width/depth, deck height, allowable deck loading in kg/m², proscenium versus open configuration, and house risers. Obtain measured room and stage drawings and current rated-load documentation from the responsible venue facilities/engineering office.
-
Curfews / restrictions: The planning assumption is curtain 22:00 on 26 June 2027 plus 150 minutes, finishing at 00:30 on 27 June. Hard event-end time: UNVERIFIED — conflict cannot be determined. Applicable quantitative noise limit, measurement location and conditions: UNVERIFIED; a noise restriction is distinct from an event hard cutoff. Barangay and Dumaguete city permit conditions, venue/heritage/structural restrictions and date-specific approval: UNVERIFIED. Any midnight load-out deadline and its separate operational conflict with a 00:30 finish are UNVERIFIED; do not treat a possible load-out deadline as a confirmed event curfew. 1
-
House equipment: UNVERIFIED: house PA and audio, lighting, video/LED, backline, drapes, risers and specifically excluded items. No inventory or exclusion schedule was found; absence of a listing is not evidence that equipment is absent.
-
Production contact: Dedicated production contact, venue management office, named production officer and direct venue email/phone: UNVERIFIED. As an escalation route, the provincial directory lists the Provincial Engineer's Office under Engr. Andre M. Reyes, admin 225-1111 or 422-8887 loc 265, information loc 264; and the Provincial General Services Office under Engr. Berchmans N. Patrimonio, loc 275/278 on the same numbers 128. The provincial head-office email is governor.negor@gmail.com 128. These are public office contacts, not assigned show contacts or verified venue rigging signatories. The city engineer/building official's office lists (035) 2253401 and other numbers for general building-related matters 130. Request referral to the actual venue facility manager and authorized structural/electrical engineers.
Evidence limits: No official venue-specific rigging ratings, show electrical capacity, technical pack, production contact, applicable quantitative noise limit or enforceable event cutoff for the 2027 show were located in the public sources reviewed. Confirm facility identity, engineering, approvals and event-specific conditions with the responsible offices; no contact was made.
Advance-critical confirmations: - Confirm the Macias building, precise access address, current availability and responsible venue manager; do not adopt an earlier event’s traffic plan 126 124 128. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 16
Bohol Wisdom Gymnasium
Route stop(s) and show date(s): 16 — 10 Jul 2027. Routed location: Tagbilaran. Organizer planning capacity: 2,500. 1
Identity and routing: The best match is Bohol Wisdom School Gymnasium in Tagbilaran City, named in a school letter and Department of Education memorandum 131. The school's 2026 letterhead gives 0575 CPG North Avenue, Booy District, Tagbilaran City, Bohol 132; a map locates the gym on Carlos P. Garcia North Avenue 133, while a venue listing uses MV64+3FG, North Road, Tagbilaran 134. Confirm the exact building and truck entrance with the school; the street and map references are not a surveyed loading address. The provincial inventory separately lists UB Gym on Maria Clara Street; do not substitute it for Bohol Wisdom School Gymnasium 135. Organizer's 2,500 is a planning figure; approved event occupancy is UNVERIFIED.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Bohol Wisdom School administration, for referral to its facilities/structural engineer 132. UNVERIFIED: roof structure and fly system, rigging point count, maximum kg per point, total allowable distributed load in kg, floor-to-grid height, approved positions, and rigging-plot review/signoff process. No venue/owner/government point or total rating was found publicly. 9 x 4 m flown LED wall: CANNOT ASSESS. 12 x 5 m flown LED wall: CANNOT ASSESS. For both, wall mass, center of gravity, point loads, approved locations and support geometry are unknown; venue ratings alone would not establish suitability without the actual wall, an engineered load/rigging plot and required approval. Ask the school's administration to route to its facilities management/engineering function; the precise responsible office is UNVERIFIED.
-
Power: UNVERIFIED: incoming service and voltage, phases, amperage per phase, tie-in location and connector, clean/stable power status, whether a generator is required, whether a generator is permitted, and whether an exclusive power provider is mandated. Obtain a current electrical single-line, usable tie-in capacity and generator rules from the school's responsible facilities/electrical function; its precise office is UNVERIFIED.
-
Load-in: UNVERIFIED: loading-door width and height, dock height, truck approach and access, onsite daytime siting for a 53-ft trailer, and onsite daytime tour-bus siting. Tagbilaran's 2023 citizen charter states that the City Administrator's special-permit procedure for crowd activities calls for CTMO and city police approvals for those using streets 136. Any road closure, actual route, truck restrictions and event-specific permit conditions remain UNVERIFIED.
-
Stage: UNVERIFIED: stage width and depth, deck height, stage loading in kg/sq m, proscenium versus open configuration, and house risers. The province's 2015 inventory estimates the Bohol Wisdom School Gymnasium area at 450 sq m 135; that historic figure is not a stage measurement, load rating or approved audience capacity.
-
Curfews / restrictions: Planned 22:00 curtain plus 150 minutes ends at 00:30 on 11 Jul 2027, the following calendar day. Hard event end: UNVERIFIED — conflict cannot be determined. Midnight load-out deadline and any separate load-out conflict: UNVERIFIED. The 2023 city charter describes a special-event permit through the Mayor's Business Permit and Licensing Office, including a request letter approved by the Mayor or City Administrator and a police endorsement 136; this is general procedure, not a verified permit or cutoff for this show. Barangay conditions, heritage and structural restrictions: UNVERIFIED. The city council's 2021 summary of pandemic-era Ordinance C-314 describes a 60 dB recommended volume for video karaoke devices and a deemed excess on three neighboring-household complaints 137. The actual current ordinance text and its applicability to this concert are UNVERIFIED; do not treat that device-specific noise summary as a hard event-end time or an established concert-wide limit. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes and specifically excluded items. Obtain a current itemized inventory and exclusions from the school's responsible venue/facilities office; no equipment should be assumed present or absent.
-
Production contact: Bohol Wisdom School administration is the best published starting point for referral to gym facilities and engineering. School letterhead dated January 2026 gives (038) 412-5150 / 411-4405 and bws.edu.ph@gmail.com, and names Dr. Raul H. Deloso as Head, Administrative Team 132. These are general school details, not a confirmed production assignment. Dedicated venue production contact and precise facilities/engineering office: UNVERIFIED.
Evidence limits: No public exact-venue rigging, structural, electrical or production specification was located. The school website was login/captcha gated; its 2026 letterhead and other public records were readable. The city council's ordinance summary was accessible, but the complete current ordinance and its application to this concert were not verified. Venue approvals, event-specific permits and overnight conditions require confirmation.
Advance-critical confirmations: - Confirm the school gym, delivery entrance and approved capacity; obtain the current noise text and school-specific overnight conditions 131 132 137. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 17
Kalibo Municipal Gymnasium
Route stop(s) and show date(s): 17 — 17 Jul 2027. Routed location: Kalibo. Organizer planning capacity: 2,000. 1
Identity and routing: UNVERIFIED exact routed building and street address. The Municipality of Kalibo's 2024 tender names a Kalibo Gymnasium project in Barangay Nalook, Kalibo, Aklan 138; a DILG project record names the same locality and the municipal LGU as implementing unit and shows ON-GOING with no actual completion date, but its update date is unclear 139. K5 News calls a gym under construction in Nalook the Ati-Atihan Gymnasium and reports phase 1 began in September 2024 140; this is a strong candidate, not confirmed by the route or an operator as the booked building. Completion, commissioning, event availability and permitted occupancy for 17 July 2027 are UNVERIFIED. A separate ABL Sports Complex is at Capitol Site, Estancia, Kalibo 141, while Hala Bira identifies the Ati-Atihan Gymnasium and Kalibo Convention Center as side-by-side facilities in Nalook 142; do not substitute either other building. The organizer's 2,000 capacity is a planning figure, not verified approved occupancy.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Kalibo Municipal Engineer, as a referral lead only; venue operator and authority unverified 143. UNVERIFIED: roof structure and fly system; available point count; maximum kg per point; total allowable distributed kg; approved points, supporting geometry, floor-to-grid height, and rigging-plot review and signoff requirements. No venue/owner/government rigging ratings for this exact routed room were located. For a 9 x 4 m flown LED wall: CANNOT ASSESS. For a 12 x 5 m flown LED wall: CANNOT ASSESS. Wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown; even published venue ratings alone would not establish a pass/fail without the actual wall, an engineered load calculation and plot, and approval by the responsible engineer/operator.
-
Power: UNVERIFIED: electrical service voltage, phase configuration, amperage per phase, tie-in location, clean/stable power, utility supplier to the actual building, generator requirement, generator permission and any exclusive provider. Obtain verified electrical single-line drawings and written terms from the responsible operator and electrical engineer.
-
Load-in: UNVERIFIED: load-in door clear width and height, dock height, truck approach and access, onsite all-day siting for a 53-ft trailer, onsite all-day siting for a tour bus, and the specific municipal or barangay permits and road-closure conditions. Building identity and an exact access address must be confirmed first.
-
Stage: UNVERIFIED: stage width and depth, deck height, stage floor load rating in kg/sqm, open versus proscenium configuration, and house risers. Request surveyed dimensions and the responsible engineer's published design/load limits.
-
Curfews / restrictions: The planning assumption is a 22:00 curtain on 17 July 2027 and a 150-minute show, ending at 00:30 on 18 July, the following calendar day. Hard event end and an actual quantitative noise restriction applicable to this site and date are UNVERIFIED — conflict cannot be determined. Kalibo police mention enforcement of noise regulations, including videoke/karaoke time limits, but the announcement gives no applicable hours or decibel limit for this concert 144; noise regulation is not itself a confirmed hard event cutoff. Barangay and municipal event-permit conditions, heritage restrictions and structural restrictions are UNVERIFIED. A midnight load-out condition is also UNVERIFIED; if imposed, assess its separate conflict with the planned 00:30 show finish. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes, and specifically excluded items; no venue-issued inventory or technical rider was located. Do not assume availability or absence from the organizer's capacity figure.
-
Production contact: Assigned venue operator, production contact and their email/phone: UNVERIFIED. For the Nalook project, the municipal engineering office is a reasonable first specification request, but its venue-management responsibility is UNVERIFIED. The municipal directory lists Municipal Engineer Engr. Amalia Francisco and phone 268-4116 143; a 2 June 2026 municipal council post also names her as Municipal Engineer 145. The two publications use different middle initials, so verify her identity and current role; she is not identified as the assigned production contact. The municipality publishes business-permit inquiries at bpldkalibo@gmail.com and (036) 262 1651 146, but responsibility for this specific event permit is UNVERIFIED. No outreach was made.
Evidence limits: Exact routed building and its street address remain unconfirmed. Public records identify a likely Nalook construction project, but the accessible project status may be stale. No venue-issued rigging or electrical ratings, commissioning date, or applicable show-specific curfew/noise permit was located; no contact was made.
Advance-critical confirmations: - Identify the exact contracted building and operator, then verify completion, commissioning and occupancy; the Nalook project is only a candidate 138 139 140. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 18
Tacloban City Astrodome
Route stop(s) and show date(s): 18 — 24 Jul 2027. Routed location: Tacloban. Organizer planning capacity: 3,000. 1
Identity and routing: The routed Astrodome corresponds to the Tacloban City Convention Center/Astrodome in Sagkahan, Tacloban City 147. The arena is mapped on Esperas Avenue, Tacloban 6500 148; a city directory separately gives a restaurant address at 'Tacloban City Astrodome, Real St.' 20. Confirm the correct venue entrance and truck address. The Benjamin Romualdez International Convention Center at the old Leyte Park Hotel complex is a separate project 149; Leyte Convention Center in Palo is also a different facility 150. Do not substitute either. The city awarded rehabilitation of the Tacloban City Convention Center on 15 October 2026; work scope, completion and availability on the routed date are UNVERIFIED 151.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Tacloban Convention and City Engineer as referral leads; venue responsibility unverified 152. UNVERIFIED: roof and fly system, point count, approved point locations, maximum kg per point, total allowable distributed kg, floor-to-grid height, structural supporting geometry, and required rigging-plot approval process. No venue/owner/government point or total-load ratings were found publicly. The 9 x 4 m flown LED wall: UNVERIFIED, cannot be assessed. The 12 x 5 m flown LED wall: UNVERIFIED, cannot be assessed. For each, wall mass, centre of gravity, individual point loads, approved locations and supporting geometry are unknown; an engineered load and rigging plot plus responsible structural approval are required. No safety or pass/fail conclusion is possible. Obtain current engineering data from the responsible venue facilities/engineering office; its exact identity is UNVERIFIED.
-
Power: UNVERIFIED: venue electrical service and voltage, phases, amperage per phase, tie-in location, clean/stable status, generator requirement, generator permission, and any exclusive production-power provider. Republic Act 12017 grants LEYECO II a distribution franchise in Tacloban; section 19 says the franchise is not exclusive 153. The venue's actual supplier and any event power-vendor requirement remain UNVERIFIED.
-
Load-in: UNVERIFIED: load-in door width and height, dock height, truck approach and access, onsite daytime siting of a 53-ft trailer, onsite daytime tour-bus siting, and specific city permits or road-closure conditions. Confirm the delivery gate and street address in view of the Esperas Avenue map and Real Street venue-address reference 148 20.
-
Stage: UNVERIFIED: stage width and depth, deck height, allowable deck loading in kg/sqm, proscenium versus open configuration, and house risers. Request current drawings and rated deck documentation from venue facilities or engineering.
-
Curfews / restrictions: Planning curtain 22:00 on 24 July 2027 plus a 150-minute show gives a planned finish of 00:30 on 25 July 2027. Hard event end: UNVERIFIED — conflict cannot be determined. Quantitative noise limit, its jurisdiction, hours and measurement conditions: UNVERIFIED; noise rules are not automatically an event-end cutoff. Event-specific barangay/city permit conditions and any heritage or structural restrictions: UNVERIFIED. Separately, a midnight load-out condition, if imposed, could conflict with the planned schedule; no such condition was verified. 1
-
House equipment: Audiocenter reports an installation of 30 K-LA210-DSP line-array cabinets in the arena 154. This is a supplier account, not an operator inventory or proof of current availability, operation or rigging certification. Current house PA, lighting, video, backline, drapes and specifically excluded items are all UNVERIFIED.
-
Production contact: The city's department list includes 'Tacloban Convention' and the City Engineer's Office 152; the precise office responsible for venue engineering, an assigned production contact, named officer and direct venue phone/email are UNVERIFIED. Ask the venue operator/facilities management and City Engineer's Office for specifications and signoff; exact facility responsibility remains UNVERIFIED. For general business-permit inquiries, the city's business portal lists (053) 832-5249, 0905 413 4018 and businessportal@tacloban.gov.ph 155; these are not verified venue production contacts.
Evidence limits: No public venue-specific rigging/load ratings, electrical capacity, detailed load-in or stage documentation, enforceable show-end cutoff, applicable quantitative noise limit, current equipment inventory, or direct production contact was verified. The city has awarded rehabilitation; completion and 2027 availability are unverified.
Advance-critical confirmations: - Confirm the Astrodome entrance, rehabilitation completion and event-date availability before relying on historical equipment claims 148 20 151 154. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 19
SMX Convention Center Davao
Route stop(s) and show date(s): 19 — 31 Jul 2027; 30 — 27 Nov 2027. Routed location: Davao City. Organizer planning capacity: 5,000. 1
Identity and routing: The routed venue is SMX Convention Center Davao, 3rd Level, SM Lanang Premier, J.P. Laurel Avenue, Lanang, Davao City 8000 156. It is not the similarly named Davao Convention and Trade Center on F. Torres Street 157. The route's 5,000-person planning capacity 1 exceeds the operator's 4,500 theater-layout figure for all three combined function rooms; the operator says exact capacity varies by setup 156. The booking, room combination and authorized show-specific occupancy remain UNVERIFIED.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from SMX Davao event sales, for referral to facilities management and structural engineering 156. Roof/fly system, rigging point count, maximum kg per point, total allowable distributed kg, allowed locations, plot-approval process and floor-to-grid height: UNVERIFIED; neither point nor total rating was found in the operator's public specifications. The operator's page calls function-room ceiling clearance 6 m 158, while its capacity sheet gives 5.5 m high and 4.2 m at the front and rear 156; neither is an identified floor-to-grid height. 9 x 4 m flown LED wall: UNVERIFIED, cannot assess. 12 x 5 m flown LED wall: UNVERIFIED, cannot assess. Each needs its actual mass, center of gravity, support geometry, point loads and locations, an engineered rigging plot and venue signoff; no wall is established safe by a venue rating alone. Obtain structural ratings and approvals from SMX Davao facilities management/engineering via event sales; the precise engineering office and assigned officer are UNVERIFIED.
-
Power: Service voltage, phase count, available amperage per phase, tie-in location, clean/stable production power, generator requirement, permission to bring or run a generator, and exclusive event power provider: UNVERIFIED. Davao Light describes a Lanang substation and a franchise covering Davao City 159; this is geographic context, not confirmation of the venue's actual supply, capacity, power quality or event-provider exclusivity. Obtain written service and distribution data from SMX Davao facilities management/engineering; the exact office name is UNVERIFIED.
-
Load-in: The operator advertises two service lifts of 1,600 kg capacity each and a 4,000 kg car lift 158; these published figures are not a current engineering certification or confirmation of the tour's permitted route. Load-in door and lift-opening sizes, dock height, truck route/access, day-long onsite siting of a 53-ft trailer and tour bus, and any specific Davao City permit or road-closure conditions: UNVERIFIED. Ask the venue and city traffic authorities for measured access, current lift certifications, vehicle turning and parking approvals.
-
Stage: Stage dimensions, stage-deck height, stage-deck kg/m² rating, proscenium versus open-stage configuration, and house risers: UNVERIFIED. Separately, the operator's website states function-room floor load capacity of 100 lb/ft² (approximately 488.2 kg/m² mass-equivalent) 158; this is not a stage-deck rating, point-load rating or engineering signoff, and its applicability to the proposed configuration needs confirmation. The capacity sheet lists all combined function rooms as 4,723 m² 156, a room area rather than stage dimensions.
-
Curfews / restrictions: A 22:00 curtain and 150-minute show plan finishes at 00:30 the following day: 1 Aug and 28 Nov 2027. Applicable hard event end: UNVERIFIED — conflict cannot be determined. Davao City Ordinance 0420-10 lists general-area noise limits: Class B, a primarily commercial area, 65 dB daytime (09:00–18:00), 60 dB morning/evening (05:00–09:00 and 18:00–22:00), and 55 dB nighttime (22:00–05:00); Class AA quiet areas, including those within 100 m of specified sensitive uses, have 50/45/40 dB respectively 160. Site and receiving-area classification, measurement method/location, current amendments and applicability to the event are UNVERIFIED. Separately, the Philippine Information Agency reports Davao police guidance that the city anti-nuisance ordinance regulates late-night noise, including karaoke, from 22:00 to 05:00 161; a noise rule is not itself proof of a hard event-end cutoff. City PSSO says events applying for a Special Mayor's Permit undergo safety-cluster assessment for a certificate 162; this event's city/barangay conditions are UNVERIFIED. Heritage or other structural restrictions and any midnight load-out deadline are UNVERIFIED; if a midnight load-out condition exists, it would separately conflict with a 00:30 finish, but is not confirmed. 1
-
House equipment: House PA, lighting, video, backline, drapes, house risers and specifically excluded production items: UNVERIFIED. Function-room capacities and the operator's general event-facility descriptions do not establish a production inventory 156 158. Obtain the actual inventory, availability, hire terms, exclusions and accredited/exclusive supplier rules from the SMX Davao event-sales team and facilities management.
-
Production contact: Published SMX Davao event-sales contact: eventsales@smxcc.com.ph; +63 82 285 1045, shown on the operator's Davao capacity sheet 156. No named production officer or exact engineering-office title is publicly verified; request referral to SMX Davao facilities management/engineering for engineering specifications and rigging signoff. For city permit and safety coordination, Davao City Public Safety and Security Office lists psso@davaocity.gov.ph and 295-7722 / 295-3636 162; the city Business Bureau lists busbureau@davaocity.gov.ph and (082) 241-1000 local 377/378 163. These are city offices, not assigned venue production contacts.
Evidence limits: Public operator materials do not verify roof point or total rigging ratings, floor-to-grid height, production service amperage, a show-specific hard event end, or the 2027 permit conditions. The area classification, measurement method and current amendments governing the cited noise table need authoritative confirmation.
Advance-critical confirmations: - For each date, confirm the SMX room combination and approved occupancy, reconcile ceiling-height statements, and obtain lift certification and date-specific permits 156 158. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 20
Limketkai Atrium
Route stop(s) and show date(s): 20 — 14 Aug 2027. Routed location: Cagayan de Oro. Organizer planning capacity: 4,000. 1
Identity and routing: The routed venue matches the Atrium, East Concourse, ground floor of Limketkai Mall's main building, beside the Rotunda in Limketkai Center 164. Address: Limketkai Drive, Lapasan, Cagayan de Oro City, Misamis Oriental 9000, Philippines 165. The similarly named Event Center is a separate listing in the West Wing, not the routed Atrium 166; the Rotunda is adjacent, and the Luxe Hotel is in the same complex, not the identified room 164 165. No routed-city discrepancy found. The operator advertises up to 5,000 standing/cocktail or 2,612 theatre-style 164; the organizer's 4,000 is a planning figure, not a verified approved concert capacity. Confirm the precise Atrium footprint and approved audience capacity for the proposed layout.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Limketkai venue inquiries, for referral to Atrium facilities engineering 167. UNVERIFIED: roof/fly-system type and supporting structure, point count, maximum allowable kg per point, total allowable distributed kg, approved positions and geometry, floor-to-grid height, and rigging-plot approval process. No exact-venue point or cumulative load rating was publicly located. The 9 x 4 m flown LED wall: UNVERIFIED, cannot assess. The 12 x 5 m flown LED wall: UNVERIFIED, cannot assess. Wall masses, centers of gravity, point loads, locations, support geometry and engineered plots are unknown; venue engineering and its authorized structural signatory must review and approve each actual design. A venue rating alone would not establish that either wall is safe.
-
Power: UNVERIFIED: Atrium event supply voltage and service, phase count, amperage per phase, tie-in location, clean/stable status, actual utility provider, whether a generator is required or permitted, and whether a particular power or generator provider is exclusive. A 2015 application filed with the energy regulator reports CEPALCO's Cagayan de Oro distribution franchise with named barangay exceptions 168; this does not establish the Atrium's actual connection or event-power contractor. Obtain the venue's single-line diagram and available production loads from the responsible facilities/engineering team.
-
Load-in: UNVERIFIED: access doors and clear width/height, dock height, truck route and access restrictions, onsite 53-ft trailer day siting, tour bus day siting, and exact Cagayan de Oro or Barangay Lapasan permit and road-closure conditions. Obtain a dimensioned route from the venue facilities/operations team and confirm any public-road use with the responsible city traffic and permit authorities; no road closure is assumed.
-
Stage: The operator describes the Atrium as an indoor event space and publishes 2,989 sqm total area and 1,538 sqm ground-floor area 164; these are not stage dimensions or stage load limits. Stage width/depth, deck height, kg/sqm rating, actual proscenium versus open staging configuration, and house risers are UNVERIFIED.
-
Curfews / restrictions: The supplied plan is a 22:00 curtain on 14 Aug 2027 with a 150-minute show, ending 00:30 on 15 Aug 2027. Hard event end: UNVERIFIED — conflict cannot be determined. The city government reported that Section 614 of Ordinance 4373-94 restricts karaoke, videoke and similar sound devices in covered business establishments from midnight to 05:00 unless fully enclosed and properly soundproofed; the proposed 22:00–05:00 amendment was described as a proposal in July 2026, not established as enacted 169. The city council also describes the existing rule and its closed, soundproofed-premises exception 170. The operative text and current amendments, application to this event and room, soundproofing, quantitative dB restriction and measurement conditions are UNVERIFIED; a sound-device restriction is not automatically a hard event-end time. Mall visitor hours are 10:00–21:00 165 but do not establish a show curfew. Barangay/city event-permit conditions and heritage or structural restrictions are UNVERIFIED. A midnight load-out deadline, if imposed, would separately conflict with a 00:30 finish; the actual load-out deadline is UNVERIFIED. 1
-
House equipment: Operator marketing says the Atrium includes complimentary chairs, tables, railings and a private comfort lounge 171; quantities and contractual availability for this show are UNVERIFIED. House PA, lighting, video/LED, backline, drapes and any specifically excluded production items are UNVERIFIED. Published audience capacity does not establish equipment inventory.
-
Production contact: Limketkai Center's public venue-inquiry contact is info@limketkaicenter.com 167; the mall concierge lists (088) 856-5228 and info@limketkai.com.ph 165. A Limketkai Center venue-rental post lists 0917 717 0203 and marketingasst@limketkai.com.ph for rental inquiries 172. No assigned production contact or named technical officer is verified. Ask the venue-inquiry team to identify the Atrium facilities management/engineering office and the authorized structural and electrical signoff contacts; the precise office name is UNVERIFIED.
Evidence limits: No exact-venue engineering rider, point or distributed-load ratings, event-power capacity, stage or loading measurements, or approved date-specific permit was located publicly. The city government's and council's accounts of Section 614 were read, but the complete operative ordinance and any later amendment could not be verified in an accessible authoritative text; room and event applicability are unresolved. The operator's audience figures are marketing configuration claims, not production-specific occupancy approval.
Advance-critical confirmations: - Confirm the East Concourse Atrium footprint and approved capacity, not the separate West Wing Event Center; obtain the operative Section 614 text and applicable exception 164 166 169 170. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 21
GenSan City Gymnasium
Route stop(s) and show date(s): 21 — 21 Aug 2027. Routed location: General Santos. Organizer planning capacity: 3,500. 1
Identity and routing: Best match: General Santos City (Lagao) Gymnasium, also called Lagao Gym, at Tiongson Street, Barangay Lagao, General Santos City; the national Professional Regulation Commission links the city and Lagao names 173, and the local education office gives the street address 174. Do not substitute the separately listed Lagao National High School gym in Purok Malakas, Barangay San Isidro 175, or the separately listed Antonio C. Acharon Sports Complex 176. The city lists a 2026 Lagao Gymnasium improvement tender; work status and effects on August 2027 are UNVERIFIED 177. The organizer's 3,500 is a planning figure, not a verified current event capacity; an Inquirer report called the gym 6,000-seat in 2011, not a current approval 178. Confirm the exact site, current configuration, authorized event capacity and construction status.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from Sports and Games Development Division and City Engineer’s Office 176 179. UNVERIFIED: roof structure and fly system, approved point count and locations, maximum kg per point, total allowable distributed kg, floor-to-grid height, and rigging-plot approval procedure. No exact-venue point or total load ratings were found in a primary publication. The 9 x 4 m flown LED wall: UNVERIFIED, cannot be assessed. The 12 x 5 m flown LED wall: UNVERIFIED, cannot be assessed. For each, wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown; even published venue ratings alone would not establish suitability without the actual wall data, engineered loads and plot, and written approval. Request them from the city sports-facility operator and City Engineer's Office 176 179.
-
Power: UNVERIFIED: venue electrical service and voltage, number of phases, amperage per phase, tie-in location, clean/stable supply, generator requirement, permission for a generator, and exclusive production power provider. SOCOTECO II's 2017 interruption notice lists Leon Llido Street going to Lagao Gymnasium among an affected feeder area, but does not establish the gym's current meter, service capacity, or exclusive event supplier 180. Request the current single-line diagram, electrical assessment and written generator/provider conditions.
-
Load-in: UNVERIFIED: loading-door width and height, dock height or grade-level access, truck route and turning/entry access, permission and dimensions for on-site 53-ft trailer day siting, tour-bus day siting, and specific city/barangay permit or road-closure conditions. Obtain an access plan and written parking/traffic conditions for this site; do not assume public-street occupation is permitted.
-
Stage: UNVERIFIED: stage/deck width and depth, deck height, floor and deck load rating in kg/sqm, proscenium versus open configuration, and house risers. Request current measured drawings and certified deck/floor loads from the venue operator and City Engineer's Office 176 179.
-
Curfews / restrictions: Planning curtain 22:00 on 21 Aug 2027 plus 150 minutes gives a planned show end of 00:30 on 22 Aug 2027. Enforceable hard event end: UNVERIFIED — conflict cannot be determined. The city's published 2013 codification, Title 24 Chapter II, includes a 02:00–05:00 prohibition on disturbing sleeping people, with stated exceptions, and section 5(b) separately mentions 23:00–04:00 in a passage around loudspeaker exceptions; current validity and application to this indoor concert need city confirmation. It also distinguishes business-advertising loudspeakers from certain indoor-audience uses 176. These noise provisions are not established here as a hard show cutoff; no applicable quantitative dB limit was verified. Barangay/city permit-specific conditions, heritage and structural restrictions, and any midnight load-out deadline are UNVERIFIED. If a midnight load-out deadline exists, assess it separately from show-end curfew. 1
-
House equipment: UNVERIFIED: house PA and audio control, lighting and control, video/LED and projection, musical backline, drapes, and the equipment or services specifically excluded from a rental. A historical seating estimate does not establish the present production inventory 178. Obtain an itemized current inventory, condition and inclusion/exclusion list.
-
Production contact: The city's 2013 code designates the City Mayor's Office Sports and Games Development Division to manage city-owned sports facilities including the General Santos City Gymnasium; the City General Services Office supplies and inventories the facilities/equipment list 176. The city directory lists Sports and Games Development Division telephone 302-0860; no usable division email is published in that listing. General Services: 554-0867, cgso.gensan1061@gmail.com; City Engineer's Office: 301-8142 179. PIA identified Lady Margaret Manalo as division chief in 2025, not as the assigned production contact; her present role and the show's assigned contact are UNVERIFIED 181. Ask the sports division to direct structural and electrical questions to the responsible city engineering/facilities personnel.
Evidence limits: No exact-venue technical specification or verified load/service ratings located. Current applicability of the 2013 noise code, 2027 permit terms, exact service provider and construction impacts remain unverified; the 2026 tender's detailed bidding documents required supplier login and were not accessed. Public sources only; no contact, login or booking.
Advance-critical confirmations: - Confirm the Lagao gym booking, construction impact and current capacity, plus the applicability of the codified noise provisions 173 176 177. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 22
Iligan City Civic Center
Route stop(s) and show date(s): 22 — 04 Sep 2027. Routed location: Iligan. Organizer planning capacity: 2,500. 1
Identity and routing: UNVERIFIED — exact physical building, street address, municipality, owner, operator and room remain unidentified. The routing lists Iligan City Civic Center in Iligan and 2,500 as an organizer planning figure, not a verified venue or licensed capacity 1. The similarly named Mindanao Civic Center Gymnasium is in Tubod, Lanao del Norte, not Iligan 182. Ilagan City Civic Center is in a differently spelled city in Isabela 183, at Barangay Alibagu 184. Neither is established as the routed venue; do not substitute either.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from if Iligan is confirmed, City Engineer or City Sports Office as referral leads; venue authority unverified 185. UNVERIFIED — roof/fly system, available point count, maximum kg per point, total allowable distributed load in kg, approved attachment locations, floor-to-grid height and rigging-plot approval process. No exact-venue point or cumulative rating was located. A 9 x 4 m flown LED wall: UNVERIFIED, cannot assess. A 12 x 5 m flown LED wall: UNVERIFIED, cannot assess. For each, wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown; engineered loads and a plot approved by the responsible venue/structural engineer are required even if venue ratings are later supplied. No pass/fail or safety assumption is possible.
-
Power: UNVERIFIED — actual site electricity supplier, service voltage, phase configuration, amperage per phase, tie-in location, clean/stable power, generator requirement, generator permission and exclusive show-power provider. In a 2013 regulatory application, Iligan Light and Power, Inc. stated that it held Iligan City's electric-distribution franchise 186; this historical city-level statement does not identify the unresolved building's supply or an exclusive production-power provider.
-
Load-in: UNVERIFIED — loading-door width and height, dock height, truck route/access, onsite siting of a 53-ft trailer for the day, onsite siting of a tour bus for the day, and actual barangay/city permits or road-closure conditions. No particular site or access route has been established.
-
Stage: UNVERIFIED — stage width and depth, deck height, floor/deck capacity in kg/sqm, proscenium versus open configuration and house risers. The routing's 2,500 figure is a planning assumption, not proof of stage dimensions, allowable capacity or equipment 1.
-
Curfews / restrictions: The 04 Sep 2027 routing date is supplied 1; the requested 22:00 curtain plus 150 minutes plans a 00:30 finish on 05 Sep 2027. Applicable hard event end: UNVERIFIED — conflict cannot be determined. If the venue is actually in Iligan, the city government's advisory says City Ordinance No. 17-6598 restricts loud noise from speakers, radios and sound systems citywide from 22:00 to 06:00 except for permitted cases 187. This is an official advisory, not the ordinance text or a demonstrated unconditional show cutoff; applicability, any noise permit and its terms for the actual site and date remain UNVERIFIED. A quantitative dB limit is UNVERIFIED. Barangay/city event permit conditions, structural and heritage restrictions are UNVERIFIED. For identity comparison only, PIA reports that the separate Mindanao Civic Center complex in Tubod was declared an Important Cultural Property in 2024 188; do not apply this to the unresolved routed site. A midnight load-out deadline is UNVERIFIED; if imposed, it would separately conflict with the 00:30 finish and required post-show load-out, not establish a hard event-end curfew by itself. 1
-
House equipment: UNVERIFIED — house PA, lighting, video equipment, backline, drapes and all specifically excluded items. The organizer's capacity figure does not establish equipment availability 1.
-
Production contact: UNVERIFIED — exact venue operator, facilities-management/engineering office and assigned production contact. If the site is confirmed in Iligan, the city directory lists City Engineer's Office head Engr. Leonor T. Actub, 221-4645 / 09159859637, ceo@iligan.gov.ph, and Iligan City Sports Office OIC head Karl Joseph P. Badelles, 0962-738-5969, citysports@iligan.gov.ph 185. These are general city-office leads for referral, not verified venue contacts or appointed show engineers; the confirmed operator's facilities/engineering office must supply venue-specific data.
Evidence limits: Exact Iligan City Civic Center building and address could not be independently verified. No venue-specific primary technical specification or assigned production contact was found. The full text and current application of the Iligan anti-noise ordinance could not be independently verified; its official advisory is conditional on the venue actually being in Iligan.
Advance-critical confirmations: - Identify the contracted physical building, municipality, address and operator before any specification is assumed; neither Tubod nor Ilagan is an established substitute 182 183 184. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 23
Butuan City Sports Complex
Route stop(s) and show date(s): 23 — 11 Sep 2027. Routed location: Butuan. Organizer planning capacity: 2,500. 1
Identity and routing: The routed name matches Butuan City Sports Complex, Barangay Libertad, Butuan City, as named in a government report 189. A 2000 presidential proclamation describes the proposed complex and government-center site as Km. 3, Barangay Libertad, and historically redesignated that site the Butuan City Multi-Purpose Training Center; the present street entrance is UNVERIFIED 190. The city identified a Festival Center within the Libertad complex 191 and a JC Aquino Building there 192; which space is booked is UNVERIFIED. Do not confuse it with the separately identified Butuan City Polysports Complex in Barangay Tiniwisan, where an oval rehabilitation was launched in July 2026 193.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from City Building Management and City Engineering; responsibility for the booked room unverified 194 195. UNVERIFIED: roof/fly system, point count, maximum kg per point, total allowable distributed load in kg, floor-to-grid height, approved locations, supporting geometry, and required rigging-plot approval. No exact-venue owner/engineering point or total rating was found. The 9 x 4 m flown LED wall cannot be assessed; the 12 x 5 m flown LED wall separately cannot be assessed. For both, wall mass, center of gravity, point loads and support geometry are unknown; venue ratings alone would not establish safety without the actual wall data, engineered loads/plot and approval. Request engineering data and written signoff from the responsible facilities management/engineering office; precise venue authority UNVERIFIED.
-
Power: UNVERIFIED: actual service voltage, phases, available amperage per phase, tie-in location, clean/stable status, whether a generator is required or permitted, and any exclusive provider. ANECO's 2021 interruption advisory listed a Sports Complex among areas affected by the Libertad substation circuit; the exact present service connection is UNVERIFIED 196. A city 2025 festival tender for a 'Sports Complex' specified a rental 150 kVA generator; this was a historical event procurement, not the venue's permanent power capacity or a 2027 requirement 197.
-
Load-in: UNVERIFIED: loading-door sizes, dock height, truck access and turning route, whether a 53-ft trailer can be sited onsite for the day, and whether a tour bus can be sited onsite for the day. Specific city/barangay permit, curb-use or road-closure conditions are UNVERIFIED. A historic proclamation noted parking and potential highway congestion concerns at the Libertad site, not present-day vehicle clearance or capacity 190.
-
Stage: UNVERIFIED: booked performance area's dimensions, stage dimensions, deck height, kg/sqm load rating, proscenium versus open configuration, and house risers. The 2025 festival tender for a 'Sports Complex' specified a rented 32 ft x 44 ft non-slip stage platform, not an existing house stage or proof that the 2027 performance space has those dimensions 197.
-
Curfews / restrictions: A 22:00 curtain on 11 Sep 2027 plus 150 minutes ends at 00:30 on 12 Sep 2027. Hard event-end time UNVERIFIED — conflict cannot be determined. Butuan's Business Permits and Licensing Department reports enforcement of city Noise Pollution Abatement Ordinance 2395-2002 by measuring sound-emitting devices 198; the actual ordinance text, current quantitative dB limit, applicable site classification and measurement/time conditions are UNVERIFIED. Noise restrictions are not automatically a hard event cutoff. Barangay/city permit conditions and heritage or structural restrictions are UNVERIFIED. Any separate midnight load-out deadline and resulting load-out conflict are also UNVERIFIED. 1
-
House equipment: House PA, lighting, video/LED, backline, drapes and specifically excluded items: UNVERIFIED. A city 2025 Balangay Festival tender requested rental sound, lighting, LED, band instruments, stage and trusses for a 'Sports Complex' 197; this does not establish permanent house inventory or 2027 availability.
-
Production contact: Venue production contact and responsible operator/engineering office for this exact booked space: UNVERIFIED. The city's directory lists Engr. Nelson P. Resus as City Building Management Department head 194, not as an assigned venue production contact; City Engineering Department is also published 195. These are potential offices to identify the responsible facility engineer and supply specifications. The Department of Trade and Industry's 2021 city profile lists general city hall phone 085 817-5598 and cmo.butuan@gmail.com 199; current status and direct connection to this venue are UNVERIFIED. No venue-specific phone or email verified.
Evidence limits: The named Libertad complex is supported, but the exact booked space and responsible venue officer are not identified. Searches did not find exact-venue engineering ratings, current house inventory, the text and site classification of the noise ordinance, or a dated event permit. Historical festival rental requirements and an electrical interruption advisory are not current venue certifications. No one was contacted.
Advance-critical confirmations: - Confirm the exact booked room and operator within the Libertad complex; do not transfer the Tiniwisan facility or historical festival rental specifications 189 193 197. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 24
Zamboanga City Coliseum
Route stop(s) and show date(s): 24 — 18 Sep 2027. Routed location: Zamboanga City. Organizer planning capacity: 3,500. 1
Identity and routing: The routed Zamboanga City Coliseum was renamed Mayor Vitaliano D. Agan Coliseum by Zamboanga City Ordinance 352; the ordinance identifies the existing coliseum as being in Tetuan 200. The City General Services Office gives its location as inside the ZCHS-Main campus, Don Alfaro St., Barangay Tetuan, Zamboanga City 201. Do not confuse it with the Joaquin Enriquez Memorial Sports Complex in Baliwasan 202, or the separately reported Zamboanga City Arena project in Calarian 203. Organizer planning capacity is 3,500, not a verified approved show capacity 1. Confirm the contracted building and event-specific capacity.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from City General Services and City Engineer; venue-specific signoff authority unverified 201 204. UNVERIFIED: roof/fly system, usable point count, maximum kg per point, total allowable distributed kg, approved attachment geometry and locations, floor-to-grid height and rigging-plot approval process. No venue/owner/government point or cumulative load rating was found publicly. The 9 x 4 m flown LED wall is UNVERIFIED and cannot be assessed; separately, the 12 x 5 m flown LED wall is UNVERIFIED and cannot be assessed. Wall mass, center of gravity, individual point loads and supporting geometry are unknown for both. Even published ratings alone would not establish a safe wall: require the actual wall data, engineered loads and plot, and written approval. Ask the City General Services Office and City Engineer’s Office for the responsible structural authority; the venue’s specific rigging approval office is UNVERIFIED 201 204.
-
Power: UNVERIFIED: electrical service and voltage, phases, available amperage per phase, tie-in location, clean/stable status, utility provider to this building, whether a generator is required, whether it is permitted, and whether any power or generator provider is exclusive. Request a current electrical single-line diagram and measured/approved capacity from the responsible venue facilities/engineering office; the exact office responsible for this building is UNVERIFIED.
-
Load-in: UNVERIFIED: load-in door widths and heights, dock height, truck access and turning, onsite 53-ft trailer siting for the day, onsite tour-bus siting for the day, and any specific city or barangay permits, restrictions or road-closure conditions. The published location is on the ZCHS-Main campus 201; verify the actual entrance and vehicle path with facilities rather than assuming direct campus access.
-
Stage: UNVERIFIED: usable stage dimensions, deck height, deck loading in kg/sqm, proscenium versus open configuration, and house risers. The organizer’s 3,500 is a planning figure 1, not a published stage specification or certified capacity.
-
Curfews / restrictions: Planned curtain 22:00 on 18 Sep 2027 plus 150 minutes ends at 00:30 on 19 Sep 2027. UNVERIFIED — conflict cannot be determined: no applicable enforceable hard event end has been established. Midnight load-out deadline and any separate load-out conflict are also UNVERIFIED. City Ordinance 301 section 3.5 states a maximum 80 decibels at 3 meters from the unit for videoke/karaoke as defined by that ordinance 205; Ordinance 959 amends monitoring and penalties 206. This is not established as the limit or a hard cutoff for a live concert PA. A public post identifies a purported Tetuan Ordinance 14 of 2026 addressing amplified sound 207, but its operative text, enactment/status and applicability to this event were not independently verified. Concert-specific quantitative noise restrictions, barangay/city permit conditions, and heritage or structural restrictions are UNVERIFIED; obtain the applicable texts and show-specific conditions. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes, and specifically excluded items. Obtain a dated house inventory and rental inclusions/exclusions; the organizer’s attendance planning figure does not establish equipment availability.
-
Production contact: Dedicated venue production contact and actual operator/signoff office: UNVERIFIED. The City General Services Office is a useful first facilities lead: its published office is at Mayor Vitaliano D. Agan Coliseum, Don Alfaro St., Tetuan; telephone (062) 955-3967, (062) 991-3095 or (062) 983-1367; emails cgso_zc@yahoo.com and cgso2020addiv@gmail.com. Its page lists Engr. Rene M. Dela Cruz as department head, not as an assigned production contact; current assignment is UNVERIFIED 201. The City Engineer’s Office, which also functions as the Office of the Building Official, lists (062) 991-0101, 991-2383, 991-2384 and zambocityengineersoffice@yahoo.com 204; its specific signoff role for this venue is UNVERIFIED.
Evidence limits: Public research identified the renamed Tetuan coliseum, city facilities and engineering contacts, the city karaoke ordinance, and a purported local sound ordinance. No venue-issued engineering/production specifications, building-specific signoff authority, confirmed concert-PA noise limit, applicable hard event cutoff or event-specific permit conditions were found. The public works website blocked access to its arena procurement documents.
Advance-critical confirmations: - Confirm the Tetuan Agan Coliseum and campus entrance; obtain applicable city and barangay sound texts rather than applying karaoke-only limits to the concert 200 201 205 207. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 25
Cotabato City Gymnasium
Route stop(s) and show date(s): 25 — 02 Oct 2027. Routed location: Cotabato City. Organizer planning capacity: 2,000. 1
Identity and routing: The best match is Cotabato City Gymnasium at the People's Palace, Barangay Rosary Heights X, Cotabato City; the City Administrator identified this as the gym inaugurated on 5 October 2026 208, and an earlier city notice placed it behind the People's Palace 209. A third-party map gives approximate plus code 56XM+4VG, 7.1978218, 124.2347125; confirm the truck entrance and exact address with the operator 210. Do not confuse it with the South Cotabato Gymnasium and Cultural Center in Koronadal City 211. The mayor's 2025 post announced a planned 1,000-seat gym upgrade for 2026 212, whereas the organizer's routing lists 2,000 as a planning capacity 1. These figures may describe different occupancy configurations; current approved event capacity is UNVERIFIED.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from City Administrator and City Engineer as referral leads; actual venue authority unverified 208 213. UNVERIFIED: roof/fly system, rated point count and locations, maximum kg per point, total allowable distributed kg, floor-to-grid height, and rigging-plot approval process. No venue/owner/government point or total load rating was found. Both a 9 x 4 m flown LED wall and a 12 x 5 m flown LED wall are UNVERIFIED and cannot be assessed: actual wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown. Even published venue ratings alone would not establish safety without the actual wall, engineered loads and plot, and written approval. Seek the responsible venue facilities/engineering office; its precise identity is UNVERIFIED.
-
Power: UNVERIFIED: venue service voltage and capacity, phase count, amperage per phase, tie-in location, clean/stable status, whether a generator is required or permitted, and any exclusive event-power provider. Cotabato Light identifies itself as a distribution utility supplying Cotabato City 214; this does not verify the gym's particular supply, available tie-in capacity, or exclusivity for event production.
-
Load-in: UNVERIFIED: loading door width and height, dock height, truck approach and access, onsite 53-ft trailer siting for the day, tour bus siting for the day, and specific city permit or road-closure requirements. A city notice locates the gym behind the People's Palace 209, but does not establish any vehicle access rights or clearance.
-
Stage: UNVERIFIED: stage width and depth, deck height, floor/deck load rating in kg/sqm, proscenium versus open configuration, and availability and dimensions of house risers. Do not infer a stage from sporting or event use.
-
Curfews / restrictions: Planning input: 22:00 on 2 October 2027 plus 150 minutes ends at 00:30 on 3 October 2027 1. UNVERIFIED — conflict cannot be determined: no applicable enforceable hard event-end time was verified. Quantitative noise limit, applicable jurisdiction and conditions, barangay/city permit conditions, and heritage or structural restrictions are also UNVERIFIED. Noise restrictions are distinct from an event-end cutoff. A midnight load-out deadline, if imposed, could separately conflict with this schedule; it is itself UNVERIFIED and is not a confirmed hard event-end conflict. 1
-
House equipment: UNVERIFIED: house PA, lighting, video, backline, drapes, available inventory, and specifically excluded items. The published seating plan does not establish equipment availability 212.
-
Production contact: Venue production contact, assigned officer, direct venue email and telephone: UNVERIFIED. The City Administrator's office published the gym inauguration 208; the city separately lists an Office of the City Engineer 213. These are potential referral points, not verified venue-management or rigging-approval authorities. A 2024 city procurement notice lists the Office of the City General Services Officer at People's Palace and Engr. Scherjan Moosa C. Ibrahim as Supervising Administrative Officer/BAC Secretary, telephone (064) 552-0864, email scherjan_ibrahim@yahoo.com 215. These are historical procurement contact details, not a confirmed production assignment; current role and suitability are UNVERIFIED.
Evidence limits: No publicly readable primary-source venue engineering specifications, applicable quantitative event-noise rule, or enforceable show-end restriction was found. Venue-specific management and a current production contact remain unverified; available general-services contact details are from a 2024 procurement notice.
Advance-critical confirmations: - Confirm the People’s Palace gym and operator and reconcile the historical 1,000-seat plan against the 2,000 route figure 208 212. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 26
Koronadal City Gymnasium
Route stop(s) and show date(s): 26 — 09 Oct 2027. Routed location: Koronadal. Organizer planning capacity: 2,000. 1
Identity and routing: LIKELY MATCH, NOT BOOKING-CONFIRMED: The city announced a new multipurpose city gym behind New City Hall in 2020 216. City Hall is on General Santos Drive, Purok Villegas, Barangay Zone III, Koronadal City, South Cotabato; that is the hall's address, not a verified gym entrance address 217. In August 2025 the city said 2026 funding was intended for completion of the proposed gym 218; completion, occupancy approval, event readiness and the exact building booked for 09 Oct 2027 are UNVERIFIED. A 2020 PNA report distinguishes this project from the existing South Cotabato Gymnasium and Cultural Center downtown 219; a separately branded cultural-center booking page lists that different facility at 26 Rafael Alunan Avenue, Zone IV 220. Do not substitute it for the routed city gym. The organizer's 2,000 is a planning figure, not a verified venue occupancy rating 1.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from City Engineering Office via City Hall; exact venue facilities authority unverified 221. UNVERIFIED: roof/fly system, existence and number of approved points, maximum kg per point, total allowable distributed load in kg, rigging-plot approval process and floor-to-grid height. No exact-venue primary point or cumulative rigging ratings were found. For a 9 x 4 m flown LED wall: UNVERIFIED; cannot assess. For a 12 x 5 m flown LED wall: UNVERIFIED; cannot assess. Wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown. Even published ratings alone would not establish either wall's safety without the actual engineered loads and plot plus written approval. Seek the structural/rigging data and signoff from the responsible venue facilities management and City Engineering Office; the precise venue facilities office is UNVERIFIED.
-
Power: SOCOTECO-I lists Koronadal City in its Area 1 coverage 222, but the actual venue's metered electricity provider is UNVERIFIED. Incoming service and voltage, number of phases, amperage per phase, tie-in location, clean/stable supply, whether a generator is required, whether a generator is permitted, and any exclusive event power supplier are all UNVERIFIED. No exact-venue primary power capacity was found; request a single-line diagram, available show power and generator rules from the responsible venue engineering office.
-
Load-in: UNVERIFIED: loading-door width and height, dock height, truck approach and unloading access, whether an onsite 53-ft trailer can be sited for the day, and whether a tour bus can be sited onsite for the day. City or barangay permit requirements, road closure conditions, vehicle restrictions and approved parking locations are UNVERIFIED; obtain a site plan and written traffic/permit conditions for the exact building.
-
Stage: UNVERIFIED: stage width and depth, deck height, deck loading in kg/sqm, proscenium versus open configuration and house risers. The organizer's 2,000 planning capacity 1 does not establish approved occupancy or any stage specification.
-
Curfews / restrictions: Organizer planning: 22:00 curtain on 09 Oct 2027 plus 150 minutes gives 00:30 on 10 Oct 2027. Hard enforceable event end: UNVERIFIED — conflict cannot be determined. Applicable quantitative noise limits and their jurisdiction or conditions, barangay/city event permit conditions, and heritage or structural restrictions: UNVERIFIED. Noise limits and conditional permits are not themselves a confirmed hard event cutoff. Midnight load-out or premises-vacate deadline: UNVERIFIED; if imposed, it could separately conflict with the planned 00:30 finish. Confirm actual event, sound and load-out conditions in writing. 1
-
House equipment: UNVERIFIED: house PA, lighting, video and screens, backline, drapes, and which production items are included or specifically excluded. Do not infer equipment from the organizer's capacity or transfer inventory from the separate provincial cultural center.
-
Production contact: The City Engineering Office is a reasonable starting point for public-building engineering, but the exact venue operator, facilities management and assigned production contact are UNVERIFIED. The city's directory names Ruel C. Tianchon as City Engineer, not as this show's contact 221. The City Government publishes general telephone (083) 228-6095 and Mayor's Office email city.mayorsoffice@koronadal.gov.ph 216; direct venue/engineering telephone and email are UNVERIFIED. Request routing to the responsible venue facilities manager and engineering approver.
Evidence limits: The exact booked building and its current completion, operation and occupancy status remain unconfirmed. No venue-specific primary rigging, power, stage, loading, equipment or enforceable event-end specifications were found in the public sources opened; the DPWH gym award PDF could not be read. No contact was made.
Advance-critical confirmations: - Confirm the exact city gym, completion, occupancy and 2027 readiness; distinguish it from the separate South Cotabato provincial gym 216 218 219. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 27
Tagum City Cultural Center
Route stop(s) and show date(s): 27 — 16 Oct 2027. Routed location: Tagum. Organizer planning capacity: 2,500. 1
Identity and routing: PROBABLE, NOT CONFIRMED: Tagum City Historical and Cultural Center on the former city-hall site contains the Tagumpay Theater 223 224. The city described a 1,000-seat theater at inauguration 223, versus the organizer's 2,500 planning capacity 1; neither establishes the event's approved capacity. The center describes Rizal as the street on which it stands 225, while a publication places it on Osmeña Street 226; a commercial listing using the routed name gives Bonifacio Street and up to 800 guests 227. These may be address or listing inconsistencies, not proof of separate venues: verify the entrance and street. The city's separately named Cultural & Trade Center Pavilion is listed on Quezon Street 228 and must not be substituted. The Cultural Center of the Philippines separately names Herminigildo Balayo MD Hall for a program at City of Tagum Cultural Center 229; the routing does not identify that room. Confirm the actual building and booked room before relying on any candidate.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from center management and Office of the City Engineer; exact venue engineering authority unverified 228. UNVERIFIED: roof or fly system, number and location of points, maximum kg per point, total allowable distributed kg, floor-to-grid height, and requirements and approving authority for a rigging plot. No venue/owner rating was found publicly. For a 9 x 4 m flown LED wall: UNVERIFIED, cannot assess. For a 12 x 5 m flown LED wall: UNVERIFIED, cannot assess. Wall mass, center of gravity, point loads, approved locations and supporting geometry are unknown; neither wall can be assessed without actual wall data, engineered loads and plot, and responsible signoff. Request engineering data from center management and the Office of the City Engineer 228; the precise venue engineering authority is UNVERIFIED.
-
Power: UNVERIFIED: electrical service and utility provider, voltage, phase count, amperage per phase, tie-in location, clean/stable status, generator requirement, generator permission and exclusive supplier. The city ordinance catalogue lists Municipal Ordinance 07 s-1993 as regulating installation of gas/diesel generators 230; its full text, current status and applicability to a temporary show generator are UNVERIFIED. Seek service drawings, measured available capacity and generator conditions from center management and the City Engineer's Electrical Installation & Maintenance Division 228.
-
Load-in: UNVERIFIED: loading-door width and height, dock height, truck approach and access, onsite day siting of a 53-ft trailer and day siting of a tour bus, and any site-specific city permits or road-closure conditions. Request a dimensioned access plan and written parking and road arrangements from center management and the city's Traffic Management Office 228.
-
Stage: SunStar describes a theater auditorium stage in the Historical and Cultural Center 231. UNVERIFIED: stage width and depth, deck height, allowable deck loading in kg/sqm, proscenium versus open configuration and house risers. The city described the center's theater as 1,000-seat 223; this is not an equipment inventory or a confirmed event capacity.
-
Curfews / restrictions: Planning assumption: 22:00 curtain on 16 Oct 2027 plus 150 minutes ends at 00:30 on 17 Oct 2027. Hard event end: UNVERIFIED — conflict cannot be determined. The city council reported approval of Ordinance 923 s-2020, describing 10:00–22:00 use of videoke and similar amplified audio devices in Tagum public streets 232; the full enacted text, current status and application to this indoor show are UNVERIFIED, so this is not a confirmed indoor hard cutoff. The city ordinance catalogue also lists a 1988 sound/music volume ordinance without its operative terms 230. An 80 dB limit at 2,000 rpm in Ordinance 454 s-2010 concerns motorcycles on streets, not a concert noise limit 233. An applicable quantitative venue noise limit, measurement conditions, barangay/city permit conditions and heritage or structural restrictions remain UNVERIFIED. Midnight load-out deadline and any separate potential load-out conflict are also UNVERIFIED; obtain the actual event permit and applicable current ordinance texts. 1
-
House equipment: UNVERIFIED: house PA and audio control, lighting and control, video/projection or LED, backline, drapes and all specifically excluded items. The CCP describes a technical-theater training program at a named hall in the cultural center 229; it does not provide a venue equipment inventory or establish that equipment will be supplied for this show. Obtain an itemized inclusions/exclusions and condition list from center management.
-
Production contact: The city directory lists the Office of the City Historical and Cultural Manager and City Tourism and Cultural Office at Osmeña St., Brgy. Magugpo Poblacion, with 0953 497 1605 and tagumtourismcultural@gmail.com 228. These are published office contacts, not a named or assigned production representative. For structural and electrical data, the directory lists the Office of the City Engineer, 0970 898 9945, campilanan.jania11@gmail.com, and its Electrical Installation & Maintenance Division, local 520, kkidtf.electrical@gmail.com 228. The specific venue facilities manager, technical lead and approving engineer are UNVERIFIED.
Evidence limits: The routed room and exact entrance remain unconfirmed. No public venue engineering specifications, house inventory, load-in plan, signed sound ordinance text for Ordinance 923 or date-specific show permit was located; ratings and any applicable show cutoff remain UNVERIFIED.
Advance-critical confirmations: - Confirm the actual center, room and entrance; resolve the 2,500 versus 1,000 figures and the differing street listings, and obtain the enacted sound text 223 225 226 227 232. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Stop group 28
Mall of Asia Arena
Route stop(s) and show date(s): 28 — 06 Nov 2027. Routed location: Manila. Organizer planning capacity: 15,000. 1
Identity and routing: The routed Mall of Asia Arena is the SM Mall of Asia Arena, J.W. Diokno Boulevard, Mall of Asia Complex, 1300 Pasay City, Philippines 234. The route calls the stop Manila and gives a 15,000 planning capacity 1; the physical municipality is Pasay City in Metro Manila, not the City of Manila 234. SM Tickets places its arena office in Barangay 076, Zone 10, Pasay 235. SMX Convention Center Manila is a separate convention facility within the same larger complex, not the routed arena 236. The arena markets full-house sports capacity of 25,000, not an approved capacity for this concert configuration 234; the organizer's 15,000 remains a planning figure, not a certified house count 1.
-
Rigging: Per-point rating: UNVERIFIED kg/point; total distributed rating: UNVERIFIED kg in the reviewed sources. Request these figures from arena booking office, for referral to the responsible facilities/structural engineering office 234. An architectural project description mentions arched roof trusses, but is not an engineering or rigging certification 236. Fly/grid configuration, usable point count, maximum kg per point, total allowable distributed kg, floor-to-grid height, approved positions and venue rigging-plot approval requirements: UNVERIFIED. No venue/owner/government point or cumulative load rating was found. 9 x 4 m flown LED wall: UNVERIFIED; cannot assess. 12 x 5 m flown LED wall: UNVERIFIED; cannot assess. For both, actual wall mass, center of gravity, attachment-point loads, approved locations and supporting geometry are unknown; neither can be judged from dimensions or venue ratings alone. Obtain the engineered plot, all point and cumulative loads, venue engineering review and written rigging signoff from the responsible arena facilities/engineering office; its exact public office name is UNVERIFIED.
-
Power: Service voltage and type, number of phases, available amperage per phase, tie-in location, clean/stable power status, generator requirement, generator permission and exclusive electrical/production provider: UNVERIFIED. Utility provider for the exact arena connection is also UNVERIFIED. Obtain a current distribution schedule and tie-in approval from the responsible arena facilities/engineering office; exact office name UNVERIFIED.
-
Load-in: Load-in door width and height, dock height, truck access and turning route, onsite 53-ft trailer siting for the day, tour bus siting for the day, and specific Pasay permits or road-closure conditions: UNVERIFIED. The arena's visitor guide lists parking at the MAAX and NU MOA buildings 237; this does not establish access or suitability for either production vehicle.
-
Stage: SM says the arena can alter its seating layout and center stage for different events 238, but this is not a stage technical specification. Stage dimensions, deck height, deck loading in kg/m², actual proscenium versus open configuration and house riser inventory: UNVERIFIED. Request venue-approved drawing and deck ratings for the selected configuration.
-
Curfews / restrictions: A 22:00 curtain on 06 Nov 2027 plus 150 minutes ends at 00:30 on 07 Nov 2027. Hard event end for this date: UNVERIFIED — conflict cannot be determined. Pasay Ordinance 6010 section 5 states that on commercial or industrial property noise may not exceed local ambient by more than 8 dB at any point outside the property plane; the ordinance defines local ambient using the lowest recurring level over six minutes measured with slow response and A-weighting 239. Confirm the arena's classification, current law and measurement/enforcement for this event. Section 8, as amended by Ordinance 6132, restricts specified sound-producing devices from 23:00 to one hour after sunrise when used in or upon public streets, parks, grounds or other publicly accessible open areas, publicly or privately owned 240. Whether that open-area provision applies to this indoor show or ancillary production areas is UNVERIFIED; it is not established as an arena-wide hard event cutoff. Barangay/city permit conditions and venue-specific heritage or structural restrictions: UNVERIFIED. Any midnight load-out deadline is separately UNVERIFIED and would need assessment against the 00:30 finish; it is not itself a confirmed hard event-end conflict. 1
-
House equipment: SM reported an arena PA upgrade in preparation for the 2023 FIBA Basketball World Cup 238. The operator identifies an event-bowl centerhung SM Arena Cube with main LED active area 128 m² and top/bottom rings of 30/18 m² respectively 241. These statements do not establish the current show inventory, specification, cost or availability. Concert PA system and patching, lighting, video beyond the described Cube, backline, drapes and items specifically excluded from the production rental: UNVERIFIED. The public fan advisory prohibits patron items including pyrotechnics, two-way radios and professional recording equipment 242; it is not a production rider or proof of restrictions on authorized crew equipment.
-
Production contact: Arena booking/venue inquiry office: info@sm-arena.com; the operator says this channel can provide a promoter's packet 234. The operator identified Arnel Gonzales as Senior Assistant Vice President and General Manager of SM MOA Arena in 2025 243; current appointment and assignment to this show are UNVERIFIED. A relevant production/engineering office name, named production contact and relevant direct telephone number: UNVERIFIED. Ask the arena booking office to route the technical advance to its responsible facilities/engineering and event-production representatives.
Evidence limits: Public research found no arena-issued rigging load ratings, power capacity or production technical packet, no event-specific permit and no confirmed hard event end. The accessible Pasay ordinance copies provide conditional noise restrictions, not an established indoor-arena curfew; later amendments and 2027 permit terms require confirmation. No venue contact was made.
Advance-critical confirmations: - Confirm the Pasay arena rather than the separate SMX facility, and obtain event-specific occupancy and applicable indoor/open-area noise interpretation 234 236 239 240. - Complete the common checklist above for the named room and date(s), including both independent LED submissions, all engineering and power figures, measured access, stage/house inventory, 00:30 permission and separate load-out deadline.
Cross-venue synthesis
Identity and routing risks. The Filoil stop is routed as Pasig, whereas the named Filoil building is identified in San Juan; PhilSports Multi-Purpose Arena in Pasig is a separate building, not an alternative named in the CSV. 2 4 3 1 The Mall of Asia Arena stop says Manila, while the operator locates the arena in Pasay City, Metro Manila; this should not be read as a verified City of Manila address. 234 1
The South Cotabato Gymnasium and Cultural Center is a separate facility in Koronadal, not the People’s Palace gym in Cotabato City; it is also distinct from the city-gym project identified as a candidate for the Koronadal stop. 208 211 216 219 Dagupan and Tacloban have separate Astrodome buildings; the similarly named Ilagan Civic Center is in Isabela, while Mindanao Civic Center is in Tubod, and neither establishes the unresolved Iligan booking. 17 20 182 183 184 1 These independently sourced comparison buildings are identity checks, not CSV-named alternatives.
Readiness and occupancy priorities. Naga’s reported retrofit rebid, Tacloban’s rehabilitation award, Kalibo’s potentially stale ongoing project record, Koronadal’s planned completion and General Santos’s improvement tender all require date-specific status checks; none proves 2027 closure or readiness. 64 151 139 218 177 Baguio, Batangas, SMX Davao, Cotabato and Tagum particularly require reconciliation of the organizer plan with the differently scoped published capacity descriptions in their sections. 26 14 156 212 223 1
Published technical and schedule comparison
The table is the precise venue list for all categories below. “No verified value” means no exact-venue value was found in the supplied public research, not that no rating or service exists. The adjacent references identify relevant reviewed venue material; they are not declarations by the source that a rating is absent. 1
- Published per-point rigging ratings: none verified in the 28 records. Without a verified published per-point rating: all 28 venues in the table.
- Published total distributed rigging ratings: none verified in the 28 records. Without a verified published total rating: all 28 venues in the table.
- Published production power capacity: none verified in the 28 records. Without a verified published production power capacity: all 28 venues in the table.
- Confirmed hard event-curfew conflicts against 22:00 + 150 minutes = 00:30 next day: none established. Unverified conflict: all 28 venues in the table, including both dates at IC3 and SMX Davao. Conditional noise restrictions, historic event requirements and possible load-out deadlines are not classified as hard show-end conflicts.
SMX Davao’s advertised lift capacities and function-room floor loading are separate from roof-rigging ratings and production electrical capacity, and do not approve this production. 158 The independent 2025 Butuan festival’s 150 kVA rental generator is not a permanent house-power rating. 197
| Venue / route stops | Per point, kg | Total distributed, kg | Production power capacity | Hard-curfew conflict vs 00:30 |
|---|---|---|---|---|
| Filoil EcoOil Centre (1) 2 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Batangas City Sports Coliseum (2) 9 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Dagupan City Astrodome (3) 16 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Baguio Convention Center (4) 26 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Angeles University Foundation Sports Arena (5) 34 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Imus Sports Complex (6) 45 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Quezon Convention Center (7) 53 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Jesse M. Robredo Coliseum (8) 59 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Ilocos Norte Centennial Arena (9) 69 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Iloilo Convention Center (10) 79 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| University of St. La Salle Coliseum (11) 90 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Capiz Provincial Gymnasium (12) 100 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| IC3 Convention Center (13, 29) 106 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Ormoc City Superdome (14) 114 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Lamberto Macias Sports Complex (15) 126 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Bohol Wisdom Gymnasium (16) 131 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Kalibo Municipal Gymnasium (17) 138 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Tacloban City Astrodome (18) 147 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| SMX Convention Center Davao (19, 30) 156 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Limketkai Atrium (20) 164 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| GenSan City Gymnasium (21) 173 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Iligan City Civic Center (22) 182 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Butuan City Sports Complex (23) 189 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Zamboanga City Coliseum (24) 200 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Cotabato City Gymnasium (25) 208 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Koronadal City Gymnasium (26) 216 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Tagum City Cultural Center (27) 223 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
| Mall of Asia Arena (28) 234 | UNVERIFIED | UNVERIFIED | UNVERIFIED | UNVERIFIED |
The schedule column means insufficient evidence to decide, not “no curfew.” The individual restrictions paragraphs preserve the relevant conditional city, police, ordinance and venue sources; obtain the authoritative present text and event permit for each date. Noise and show-end restrictions must be assessed separately from a load-out deadline.
Closing advance-critical confirmations
These are the venue-specific first actions; the full common checklist and all seven fields remain open at every venue. 1. Filoil EcoOil Centre: Reconcile San Juan against the routed Pasig label, establish the exact building and approved audience count, and request current post-incident inspection and restrictions 2 4 5. 2. Batangas City Sports Coliseum: Resolve the Barangay 20/Santa Clara discrepancy, distinguish the provincial venue, and reconcile the 4,500-seat city profile with the 5,000 planning figure 11 12 14 13. 3. Dagupan City Astrodome: Confirm the Tapuac building and loading entrance, event-date availability and responsible facilities operator; distinguish the separate Tacloban Astrodome 17 20 21. 4. Baguio Convention Center: Confirm the booked hall and entrance, reconcile the city’s 2,000 Full Hall maximum with the 3,000 plan, and obtain current site-specific noise interpretation 26 27 28. 5. Angeles University Foundation Sports Arena: Confirm the main-campus contracted hall and event floor, and establish a measured freight route and current school engineering contact 34 37. 6. Imus Sports Complex: Confirm the General Castañeda Street booking against the Bacoor-labeled listing and secure the applicable actual ordinance and permit conditions 45 47 49. 7. Quezon Convention Center: Confirm the Lucena Capitol Compound room rather than either Infanta or Gumaca center, and obtain the correct provincial engineering signatory 53 55 56. 8. Jesse M. Robredo Coliseum: Confirm retrofit status, current structural certification and availability for the April date, and distinguish the coliseum from the city gym 62 64. 9. Ilocos Norte Centennial Arena: Confirm the arena entrance and current Provincial Sports Office location, and obtain the authoritative current loud-sound ordinance and event-specific exemptions 70 75 78. 10. Iloilo Convention Center: Confirm the hall combination and licensed show layout; reconcile TIEZA and tourism-directory capacities and confirm the disputed phone number 79 83 84. 11. University of St. La Salle Coliseum: Reconcile the university handbook capacities and resolve the applicable noise class and inconsistent scanned night-period endpoint; obtain current house and prop rules 93 94 97. 12. Capiz Provincial Gymnasium: Confirm the formal routed name, booked gym and exact entrance within Villareal Stadium, not the separate provincial center or civic center 100 102 103. 13. IC3 Convention Center: For each date, confirm the IC3 hall and current operator, verify the conflicting directory phone numbers, and obtain separate overnight permits 107 110. 14. Ormoc City Superdome: Confirm the Superdome loading address and current operator; obtain the authoritative enacted noise text and any event exemption 115 116 117 122. 15. Lamberto Macias Sports Complex: Confirm the Macias building, precise access address, current availability and responsible venue manager; do not adopt an earlier event’s traffic plan 126 124 128. 16. Bohol Wisdom Gymnasium: Confirm the school gym, delivery entrance and approved capacity; obtain the current noise text and school-specific overnight conditions 131 132 137. 17. Kalibo Municipal Gymnasium: Identify the exact contracted building and operator, then verify completion, commissioning and occupancy; the Nalook project is only a candidate 138 139 140. 18. Tacloban City Astrodome: Confirm the Astrodome entrance, rehabilitation completion and event-date availability before relying on historical equipment claims 148 20 151 154. 19. SMX Convention Center Davao: For each date, confirm the SMX room combination and approved occupancy, reconcile ceiling-height statements, and obtain lift certification and date-specific permits 156 158. 20. Limketkai Atrium: Confirm the East Concourse Atrium footprint and approved capacity, not the separate West Wing Event Center; obtain the operative Section 614 text and applicable exception 164 166 169 170. 21. GenSan City Gymnasium: Confirm the Lagao gym booking, construction impact and current capacity, plus the applicability of the codified noise provisions 173 176 177. 22. Iligan City Civic Center: Identify the contracted physical building, municipality, address and operator before any specification is assumed; neither Tubod nor Ilagan is an established substitute 182 183 184. 23. Butuan City Sports Complex: Confirm the exact booked room and operator within the Libertad complex; do not transfer the Tiniwisan facility or historical festival rental specifications 189 193 197. 24. Zamboanga City Coliseum: Confirm the Tetuan Agan Coliseum and campus entrance; obtain applicable city and barangay sound texts rather than applying karaoke-only limits to the concert 200 201 205 207. 25. Cotabato City Gymnasium: Confirm the People’s Palace gym and operator and reconcile the historical 1,000-seat plan against the 2,000 route figure 208 212. 26. Koronadal City Gymnasium: Confirm the exact city gym, completion, occupancy and 2027 readiness; distinguish it from the separate South Cotabato provincial gym 216 218 219. 27. Tagum City Cultural Center: Confirm the actual center, room and entrance; resolve the 2,500 versus 1,000 figures and the differing street listings, and obtain the enacted sound text 223 225 226 227 232. 28. Mall of Asia Arena: Confirm the Pasay arena rather than the separate SMX facility, and obtain event-specific occupancy and applicable indoor/open-area noise interpretation 234 236 239 240.
Source coverage: 243 unique cited URLs, including the routing CSV; the 120-source target was reached. All 28 venue research records were available. Evidence and specification gaps are stated in the venue sections.
Source access: A separate direct HTTP recheck returned a 200 response for 174 of the 243 URLs and a different response or connection error for 69. Four of the latter were readable through a separate public extraction check, so a direct-network failure does not necessarily mean a link is dead. Conversely, a 200 response does not guarantee that a full page is readable. Access can depend on network, publisher, login walls and site changes; universal live access could not be confirmed.
References
- 1Organizer Philippines 30-stop routing CSV, revision F — checked 24 Nov 2026
- 2TicketMAX: Playtime FilOil Centre venue and directions — checked 24 Nov 2026
- 3EcoOil: Filoil EcoOil Centre pilots pediatric vaccination — checked 24 Nov 2026
- 4Philippine Sports Commission: PhilSports Complex — checked 24 Nov 2026
- 5San Juan City government statement on Filoil Centre incident, 30 October 2026 — checked 24 Nov 2026
- 6San Juan City government directory — checked 24 Nov 2026
- 7San Juan City Council ordinance index, 2020 entries — checked 24 Nov 2026
- 8San Juan City Ordinance 78, Series of 2020, opening page — checked 24 Nov 2026
- 9City General Services Office Citizen’s Charter and Profile — checked 24 Nov 2026
- 10Batangas City Sports Coliseum — TicketMAX — checked 24 Nov 2026
- 11City Government of Batangas Citizen’s Charter, 2026 Third Edition — checked 24 Nov 2026
- 12Batangas City Sports Center – Coliseum — Apple Maps — checked 24 Nov 2026
- 13Barangay official cites importance of national gov’t subsidy for LGU programs — checked 24 Nov 2026
- 14Batangas City Socio-Economic, Physical and Political Profile, CY 2024 — checked 24 Nov 2026
- 15Code of General Ordinances of Batangas City — checked 24 Nov 2026
- 16Dagupan: Securing Mayor's Permit for Activities or Undertakings — checked 24 Nov 2026
- 17Dagupan City Council: 2020 Appropriation and Reversion Ordinance — checked 24 Nov 2026
- 18Bureau of Immigration Dagupan Field Office: Address Listing — checked 24 Nov 2026
- 19Mapcarta: Dagupan Astrodome — checked 24 Nov 2026
- 20Tacloban City: Restaurant Directory — checked 24 Nov 2026
- 21Dagupan City Council: Astrodome Opens Ahead of Typhoon — checked 24 Nov 2026
- 22City Government of Dagupan: Office Directory — checked 24 Nov 2026
- 23Dagupan Bids and Awards: Genset Housing at City People's Astrodome — checked 24 Nov 2026
- 24Energy Regulatory Commission: ERC Case No. 2010-005 RC — checked 24 Nov 2026
- 25City of Dagupan Citizen's Charter, 2022 — checked 24 Nov 2026
- 26Baguio City Public Information Office: Rental rates for use of convention center updated — checked 24 Nov 2026
- 27Baguio Convention and Cultural Center venue page — checked 24 Nov 2026
- 28Apple Maps: Baguio Convention Center — checked 24 Nov 2026
- 29Cordillera International Convention Hall location — checked 24 Nov 2026
- 30SunStar: Beneco cuts Convention Center’s electricity — checked 24 Nov 2026
- 31Baguio City Police Office: Silent Night Ordinance advisory — checked 24 Nov 2026
- 32Baguio City Public Information Office: Prohibitions on noise and odor pollution — checked 24 Nov 2026
- 33Baguio City Tourism, Culture and Arts Office public advisory — checked 24 Nov 2026
- 34Angeles University Foundation — Campuses and Facilities — checked 24 Nov 2026
- 35Philippine House of Representatives — SGMA at AUF Graduation — checked 24 Nov 2026
- 36AUF Sports and Cultural Center — checked 24 Nov 2026
- 37SPIN.ph — What we know about life inside the PBA Bubble — checked 24 Nov 2026
- 38Mapcarta — AUF Sports and Cultural Center — checked 24 Nov 2026
- 39Bren Z. Guiao Convention Center — checked 24 Nov 2026
- 40Angeles University Foundation — Sports and Recreation — checked 24 Nov 2026
- 41Angeles Electric Corporation — About Us — checked 24 Nov 2026
- 42Philippine Daily Inquirer — Angeles City bans loud videoke, karaoke — checked 24 Nov 2026
- 43DWCL Center for Sports and the Performing Arts — Benchmarking Towards Excellence — checked 24 Nov 2026
- 44Angeles University Foundation — Great Danes volleyball tryout notice — checked 24 Nov 2026
- 45Shakey's Super League — Imus Sports Complex venue directions — checked 24 Nov 2026
- 46City of Imus Sports Development Unit — Citizen's Charter 2024 — checked 24 Nov 2026
- 47Volleybox — Imus Sports Center arena listing — checked 24 Nov 2026
- 48City of Imus — Office of the City Engineer — checked 24 Nov 2026
- 49Cavite Provincial Information and Community Affairs Department — Ordinance 325-2021 notice — checked 24 Nov 2026
- 50City of Imus — City Sports Development Unit — checked 24 Nov 2026
- 51City of Imus — Departments and Units Directory — checked 24 Nov 2026
- 52City Government of Imus — Public landlines — checked 24 Nov 2026
- 53Provincial Government of Quezon Citizens' Charter 2026, First Edition — checked 24 Nov 2026
- 54OWWA Regional Welfare Office 4A: Grand Alagang OWWA Serbisyo Caravan request for quotation — checked 24 Nov 2026
- 55Municipality of Infanta: inauguration at Northern Quezon Convention Center — checked 24 Nov 2026
- 56Municipality of Gumaca: Celebrating Women's Month 2024 — checked 24 Nov 2026
- 57Provincial Government of Quezon department and office directory — checked 24 Nov 2026
- 58Provincial Government of Quezon contact directory — checked 24 Nov 2026
- 59Naga City Ordinance No. 2012-043: Naming the Naga City Coliseum — checked 24 Nov 2026
- 60Naga City Departments and Offices Directory — checked 24 Nov 2026
- 61Naga City events listing: Jesse M. Robredo Coliseum — checked 24 Nov 2026
- 62Naga City Citizens' Charter: Using Government Facilities — checked 24 Nov 2026
- 63Naga City: Robredo details ₱500-M JMR Coliseum rehabilitation — checked 24 Nov 2026
- 64Naga City: Flood response equipment and coliseum retrofit rebidding — checked 24 Nov 2026
- 65Naga City: Management and maintenance of city facilities — checked 24 Nov 2026
- 66Naga City: Requesting building data — checked 24 Nov 2026
- 67Naga City Ordinance No. 36 of 1949: Regulating horns and sound devices — checked 24 Nov 2026
- 68Naga City Mayor's Office contact details — checked 24 Nov 2026
- 69Palarong Pambansa 2025 — Ilocos Norte Centennial Arena — checked 24 Nov 2026
- 70Provincial Government of Ilocos Norte Citizens' Charter 2026, first edition — checked 24 Nov 2026
- 71Ilocos Norte Centennial Arena — Trip.com address listing — checked 24 Nov 2026
- 72Ferdinand E. Marcos Stadium — Archinesia, architect-provided description — checked 24 Nov 2026
- 73Daily Tribune — DOST launches National Science, Technology and Innovation Week 2025 — checked 24 Nov 2026
- 74Ilocos Norte Electric Cooperative — Area Offices — checked 24 Nov 2026
- 75Laoag City Police Station public advisory — City Ordinance No. 13-2025-026 — checked 24 Nov 2026
- 76The Ilocos Times — LC to curb use and operation of videoke and karaoke machines — checked 24 Nov 2026
- 77OWWA Regional Welfare Office I — 2025 OFW Family Day equipment rental quotation — checked 24 Nov 2026
- 78Provincial Government of Ilocos Norte — Departments and Offices — checked 24 Nov 2026
- 79TIEZA: Iloilo Convention Center — checked 24 Nov 2026
- 80Iloilo Convention Center: Contact and basic information — checked 24 Nov 2026
- 81Visit Iloilo City: Iloilo Convention Center — checked 24 Nov 2026
- 82Courtyard by Marriott Iloilo: Events and meeting spaces — checked 24 Nov 2026
- 83Tourism Promotions Board: Philippine MICE Directory, 25 February 2026 — checked 24 Nov 2026
- 84Tourism Promotions Board: Philippine MICE brochure and venue directory — checked 24 Nov 2026
- 85MORE Power: News and articles — checked 24 Nov 2026
- 86DOST-TAPI: 2023 National Science and Technology Week exhibit rental request for quotation — checked 24 Nov 2026
- 87Iloilo City Government: Department Offices — checked 24 Nov 2026
- 88Iloilo City Government: 2020 noise policy and Regulation Ordinance 2015-162 — checked 24 Nov 2026
- 89TIEZA: Contact Us and Directory of Officials and Offices — checked 24 Nov 2026
- 90TicketMAX: University of St. La Salle Coliseum – Bacolod — checked 24 Nov 2026
- 91University of St. La Salle: Bayle De La Salle — checked 24 Nov 2026
- 92DigiCast Negros: Bacolod City coliseum to be completed this year — checked 24 Nov 2026
- 93University of St. La Salle Higher Education Unit Student Handbook 2025–2026, Coliseum section — checked 24 Nov 2026
- 94University of St. La Salle Graduate Programs Student Handbook 2024–2025 — checked 24 Nov 2026
- 95University of St. La Salle Phone Directory — checked 24 Nov 2026
- 96University of St. La Salle Institutional Officers — checked 24 Nov 2026
- 97Bacolod City Ordinance No. 356, series of 2004, noise pollution — checked 24 Nov 2026
- 98Bacolod City Ordinance No. 326, series of 2003, places of amusement — checked 24 Nov 2026
- 99University of St. La Salle: ISAT-U Benchmarks University Income-Generating Projects — checked 24 Nov 2026
- 100Barangay Tiza chair on proposed use of Capiz Gymnasium — checked 24 Nov 2026
- 101Capiz Gymnasium map — checked 24 Nov 2026
- 102DPWH completes cultural, sports hub project in Capiz — checked 24 Nov 2026
- 103Roxas City: Dinggoy Roxas Civic Center redevelopment — checked 24 Nov 2026
- 104Capiz Provincial Directory — checked 24 Nov 2026
- 105Roxas City police dissemination on Ordinance 043-2020 — checked 24 Nov 2026
- 106Professional Regulation Commission Cebu agricultural engineer examination room assignment, October 2019 — checked 24 Nov 2026
- 107IEC Convention Center of Cebu / IC3 Convention Center — World Exhibitions venue listing — checked 24 Nov 2026
- 108IEC Convention Center of Cebu seats 10,000 — SunStar, 2016 — checked 24 Nov 2026
- 109Cebu Provincial Board allows Mandaue to demolish CICC — SunStar, 2023 — checked 24 Nov 2026
- 110IC3 Convention Center Cebu — Life in Cebu listing — checked 24 Nov 2026
- 111IC3 Convention Center Cebu — Primo Venues listing — checked 24 Nov 2026
- 112Cebu City Ordinance No. 2606 and Resolution No. 15-1292-2021 — signed ordinance copy — checked 24 Nov 2026
- 113Clarifications on proposed anti-noise ordinance sought — The Freeman, 12 November 2026 — checked 24 Nov 2026
- 114Department of Tourism — Ormoc City Superdome sports venue — checked 24 Nov 2026
- 115City Government of Ormoc Citizen’s Charter Handbook 2025, first edition — checked 24 Nov 2026
- 116Trip.com — Ormoc City Superdome — checked 24 Nov 2026
- 117Taga Ormoc Daily — Ormoc City Superdome guide — checked 24 Nov 2026
- 118Philippines.tv — Ormoc City government office listings — checked 24 Nov 2026
- 119Philippine Information Agency — Car-free Sundays in Tacloban — checked 24 Nov 2026
- 120Philippine Information Agency — Ormoc sports facilities and Batang Pinoy 2027 — checked 24 Nov 2026
- 121Leyte V Electric Cooperative — About Leyeco V — checked 24 Nov 2026
- 122DND Philippines Integrated News — report on Ormoc noise ordinance — checked 24 Nov 2026
- 123City Government of Ormoc — 6 October 2026 Charter Day committee meeting — checked 24 Nov 2026
- 124Negros Oriental traffic advisory, 8–9 October 2026 — checked 24 Nov 2026
- 125Mapcarta: Lamberto L. Macias Sports and Cultural Centre — checked 24 Nov 2026
- 126Dumaguete City: CVRAA opens; region's best compete for honors — checked 24 Nov 2026
- 127Negros Oriental: Temporary closure of Lamberto L. Macias Sports & Cultural Complex — checked 24 Nov 2026
- 128Provincial Government of Negros Oriental: Contact Us and office directory — checked 24 Nov 2026
- 129NORECO II scheduled power service interruption, 16 May 2026 — checked 24 Nov 2026
- 130Dumaguete City Engineer's Office: contacts and building-related services — checked 24 Nov 2026
- 131Tagbilaran City Schools Division Memorandum: Cultural Academic Invasion 2017 — checked 24 Nov 2026
- 132DepEd Bohol Advisory 03 s. 2026: Cultural Academic Invasion and school letterhead — checked 24 Nov 2026
- 133Bohol Wisdom School Gym map and address — checked 24 Nov 2026
- 134Bohol Wisdom School Gym venue listing — checked 24 Nov 2026
- 135Bohol Provincial Planning Office: 2015 sports and recreational facilities inventory — checked 24 Nov 2026
- 136Tagbilaran City Citizen's Charter, Second Edition 2023, special-permit procedures — checked 24 Nov 2026
- 137Tagbilaran City Council: City ordinance on video karaoke machines amended — checked 24 Nov 2026
- 138Municipality of Kalibo: Invitation to Bid, September 2024 — checked 24 Nov 2026
- 139DILG SubayBAYAN: Construction of the Kalibo Gymnasium project details — checked 24 Nov 2026
- 140K5 News FM Kalibo: Construction of Ati-Atihan Gymnasium — checked 24 Nov 2026
- 141Department of Labor and Employment Region VI: Handog ng Pangulo Job Fair venues — checked 24 Nov 2026
- 142Hala Bira Network: Ati-Atihan Gymnasium and Kalibo Convention Center — checked 24 Nov 2026
- 143Municipality of Kalibo: LGU offices directory — checked 24 Nov 2026
- 144Kalibo Municipal Police Station: Local ordinances enforcement announcement — checked 24 Nov 2026
- 145Office of the Sangguniang Bayan, Kalibo: 48th regular session, 2 June 2026 — checked 24 Nov 2026
- 146Municipality of Kalibo: Online Business Permit Application — checked 24 Nov 2026
- 147NMP Strengthens Maritime Workforce Opportunities at Tacloban's MEGA Job Fair — checked 24 Nov 2026
- 148Tacloban City Convention Center map — checked 24 Nov 2026
- 149Tacloban Powers Ahead with Major Infrastructure Projects to Boost Tourism — checked 24 Nov 2026
- 150PSA Provides National ID Services During DOLE Nationwide Construction Job Fair — checked 24 Nov 2026
- 151City of Tacloban Notice of Award 3, 15 October 2026 — checked 24 Nov 2026
- 152City of Tacloban departments — checked 24 Nov 2026
- 153Republic Act No. 12017, Leyte II Electric Cooperative franchise — checked 24 Nov 2026
- 154Audiocenter powers the Sound for Tacloban City Convention Center — checked 24 Nov 2026
- 155Tacloban City business portal contact information — checked 24 Nov 2026
- 156SMX Davao floor plan and capacity sheet — checked 24 Nov 2026
- 157Davao City tourism directory: Davao Convention and Trade Center — checked 24 Nov 2026
- 158SMX Davao official venue page — checked 24 Nov 2026
- 159Newest Davao Light distribution substation powers Lanang, Davao City — checked 24 Nov 2026
- 160Davao City Ordinance No. 0420-10, revised anti-nuisance ordinance amendment — checked 24 Nov 2026
- 161Davao City Police Office reminds public of rules on late-night karaoke — checked 24 Nov 2026
- 162Davao City Public Safety and Security Office — checked 24 Nov 2026
- 163Davao City processing of business permits — checked 24 Nov 2026
- 164Atrium — Limketkai Center venue listing — checked 24 Nov 2026
- 165Limketkai Mall concierge and visit details — checked 24 Nov 2026
- 166Event Center — Limketkai Center venue listing — checked 24 Nov 2026
- 167Limketkai Center venue reservation contact — checked 24 Nov 2026
- 168CEPALCO and MINERGY 2015 power-supply application filed with the Energy Regulatory Commission — checked 24 Nov 2026
- 169Cagayan de Oro city information office: proposed amendments to noise control ordinance — checked 24 Nov 2026
- 170Cagayan de Oro City Council: amendment of city's codified ordinance sought — checked 24 Nov 2026
- 171Limketkai Center commercial leasing and event spaces — checked 24 Nov 2026
- 172Limketkai Center venue-rental inquiries announcement — checked 24 Nov 2026
- 173PRC: Face-To-Face Oathtaking of the New Professional Teachers — checked 24 Nov 2026
- 174DepEd RXII SDO General Santos City: SRAA basketball friendship match — checked 24 Nov 2026
- 175South Cotabato: PMA Entrance Examination 2026 testing venues — checked 24 Nov 2026
- 176General Santos City Code of Ordinances, Ordinance No. 11, series of 2013 — checked 24 Nov 2026
- 177General Santos procurement: Improvement of Lagao Gymnasium, 26CW-GSC-040 — checked 24 Nov 2026
- 178Inquirer: General Santos mayor confident of Pacquiao win — checked 24 Nov 2026
- 179General Santos City: Departments directory — checked 24 Nov 2026
- 180SOCOTECO II: 16 July 2017 notice of power interruption — checked 24 Nov 2026
- 181Philippine Information Agency: GenSan prepares for Batang Pinoy 2025 — checked 24 Nov 2026
- 182Lanao del Norte hosts Mindanao Best of the Best Taekwondo Championships — checked 24 Nov 2026
- 183SEC, Ilagan City seal partnership to establish extension office — checked 24 Nov 2026
- 184TESDA opens innovation center in Isabela — checked 24 Nov 2026
- 185Iligan City government contact directory — checked 24 Nov 2026
- 186ILPI application for regulatory-year 2014 capital projects, ERC Case 2013-209 RC — checked 24 Nov 2026
- 187City Government of Iligan public advisory on City Ordinance 17-6598 — checked 24 Nov 2026
- 188Lanao Norte sports complex becomes first in Mindanao with World Athletics, FIFA certified facilities — checked 24 Nov 2026
- 189DSWD: El Niño-hit farmers and fisherfolk in Caraga receive government aid — checked 24 Nov 2026
- 190Presidential Proclamation No. 249, 29 February 2000 — checked 24 Nov 2026
- 191Butuan 2023 Balangay Festival lights and sounds procurement addendum — checked 24 Nov 2026
- 192Butuan Beckons: online tourism photography contest — checked 24 Nov 2026
- 193Butuan council: groundbreaking of Polysports Complex oval track rehabilitation — checked 24 Nov 2026
- 194Butuan City Government offices and department heads — checked 24 Nov 2026
- 195Butuan City Engineering Department — checked 24 Nov 2026
- 196ANECO emergency power interruption advisory, 30 January 2021 — checked 24 Nov 2026
- 197Butuan 2025 Balangay Festival technical equipment rental bidding document — checked 24 Nov 2026
- 198Butuan City Business Permits and Licensing Department: Oplan Sita night operation — checked 24 Nov 2026
- 199DTI Cities and Municipalities Competitive Index: Butuan 2021 profile — checked 24 Nov 2026
- 200Zamboanga City Ordinance No. 352: Renaming the Zamboanga City Coliseum — checked 24 Nov 2026
- 201City Government of Zamboanga: Office of the City General Services — checked 24 Nov 2026
- 202City Government of Zamboanga: Joaquin Enriquez sports complex — checked 24 Nov 2026
- 203Aviso Zamboanga: Zamboanga City Arena project update — checked 24 Nov 2026
- 204City Government of Zamboanga: Office of the City Engineer — checked 24 Nov 2026
- 205Zamboanga City Ordinance No. 301: Videoke and Karaoke Systems — checked 24 Nov 2026
- 206Zamboanga City Ordinance No. 959: Amendment to Ordinance No. 301 — checked 24 Nov 2026
- 207Public post citing Barangay Tetuan Ordinance No. 14, Series of 2026 — checked 24 Nov 2026
- 208Cotabato City Office of the City Administrator — gymnasium inauguration at People's Palace — checked 24 Nov 2026
- 209City mayor's quarterly job fair announcement — Cotabato City Gymnasium — checked 24 Nov 2026
- 210Maptons — Cotabato City Gymnasium location — checked 24 Nov 2026
- 211South Cotabato government — Dangal integrity awards in Koronadal — checked 24 Nov 2026
- 212City mayor's 2025 announcement — planned 1,000-seat gymnasium upgrade — checked 24 Nov 2026
- 213Cotabato City Government — frontline office work arrangement — checked 24 Nov 2026
- 214AboitizPower — Cotabato Light distribution utility — checked 24 Nov 2026
- 215PhilGEPS — Cotabato City medicine procurement notice, November 2024 — checked 24 Nov 2026
- 216New City Gymnasium to rise in Koronadal — City Government of Koronadal — checked 24 Nov 2026
- 217City of Koronadal invitation to bid, 25-03-0049 — checked 24 Nov 2026
- 218Infrastructure projects to rain in the City of Koronadal — checked 24 Nov 2026
- 219Ogena announces start of construction for Koronadal City's gym — PNA report — checked 24 Nov 2026
- 220South Cotabato Gymnasium and Cultural Center venue listing — checked 24 Nov 2026
- 221Koronadal city department and section heads — checked 24 Nov 2026
- 222SOCOTECO-I — office and service coverage — checked 24 Nov 2026
- 223City Government of Tagum: inauguration of the City Historical and Cultural Center — checked 24 Nov 2026
- 224Tagum City Historical and Cultural Center officially inaugurated — checked 24 Nov 2026
- 225Tagum City Historical and Cultural Center: Sentro Rizal address and gallery — checked 24 Nov 2026
- 226Tagum’s Kagikan: The museum of the Tagumenyo people — checked 24 Nov 2026
- 227Tagum City Cultural Center — Theater & Lobby Areas — checked 24 Nov 2026
- 228City Government of Tagum office directory — checked 24 Nov 2026
- 229CCP cultural exchange brings the 2026 Kaisa sa Sining apprenticeship program to Tagum City — checked 24 Nov 2026
- 230Tagum Sangguniang Panlungsod ordinance catalogue — checked 24 Nov 2026
- 231Tagum City's center for expression — checked 24 Nov 2026
- 232Tagum City Council 59th regular session: approved ordinances and resolutions — checked 24 Nov 2026
- 233Tagum City Ordinance No. 454 s-2010: motorcycle noise pollution — checked 24 Nov 2026
- 234SM Mall of Asia Arena — Book the Arena — checked 24 Nov 2026
- 235SM Tickets — Feedback & Inquiry office — checked 24 Nov 2026
- 236Mall of Asia Arena — architectural project description — checked 24 Nov 2026
- 237SM Mall of Asia Arena — A–Z Guide — checked 24 Nov 2026
- 238SM Mall of Asia Arena embodies customer service excellence for 12 years and onwards — checked 24 Nov 2026
- 239Pasay City Ordinance No. 6010, series of 2019 — official filed copy — checked 24 Nov 2026
- 240Pasay City Ordinance No. 6132, series of 2020 — official filed copy — checked 24 Nov 2026
- 241SM Mall of Asia Arena — Partner with Us — checked 24 Nov 2026
- 242SM Mall of Asia Arena — Fan advisory — checked 24 Nov 2026
- 243SM MOA Arena The Cube — Bigger centerhung to bring better fan experience — checked 24 Nov 2026